GUARANTEED MAXIMUM PRICE AMENDMENT CONSTRUCTION GMP
Exhibit 10.1
AIA 133 Attachment
Construction GMP
GUARANTEED MAXIMUM PRICE AMENDMENT
CONSTRUCTION GMP
Pursuant to Document A133 - 2009, dated the 1st day of December 2009 and the A201 General Conditions of the Contract attached thereto, between TD AMERITRADE Services Company, Inc (OWNER) and Kiewit Building Group Inc. (CONTRACTOR) for TD Ameritrade Omaha Campus (the Project), OWNER and CONTRACTOR establish the following Guaranteed Maximum Price and Contract Time for the Work.
ARTICLE I
Construction GMP
The Guaranteed Maximum Price for the Project shall be $197,000,000.00 in accordance with the GMP Manual dated November 15, 2011 and the Contract Documents. This Amendment supersedes Amendments 1-9, and those amendments are no longer valid.
Exhibit A | Construction GMP Manual dated November 15, 2011. |
ARTICLE II
CONTRACT TIME
Beneficial Occupancy of Comm / Data Rooms: December 31, 2012
Substantial Completion: April 2, 2013
Final Completion: June 19, 2013
The owner shall accept this Guaranteed Maximum Price Amendment by December 1, 2011 (the Effective Date).
AUTHORIZED AND APPROVED BY:
OWNER | CONTRACTOR | |||
TD AMERITRADE Services Company, Inc | KIEWIT BUILDING GROUP INC. | |||
/s/ William J. Gerber | /s/ Ron Duce | |||
(Signature) | (Signature) | |||
William J. Gerber, EVP/CFO | Ron Duce, Senior Vice President | |||
(Printed Name and Title) | (Printed Name and Title) |