10.24 Contract of Offering Technology Design, Key Equipments, Materials and Technique Service for Effluent Disposal Project

EX-10.24 26 c17382exv10w24.htm EXHIBIT 10.24 Exhibit 10.24
Exhibit 10.24
10.24 Contract of Offering Technology Design, Key Equipments, Materials and
Technique Service for Effluent Disposal Project
Party A: Shandong Xiangrui Pharmacy Co., Ltd (the “Company”)
Party B: Park Environment Protection Technology (Shanghai) Co., Ltd
 
Main Content:
   
The contract is entered for Party A’s effluent disposal project.
 
   
Party A would be in charge of the whole management for the project’s construction.
 
   
Party B would be in charge of offering technology design, key equipments, materials and technique service.
 
   
The function test would be made by the parties together.
 
Party B Offering:
   
Technology design package;
 
   
Key equipments for the project;
 
   
Information & handbook of the technology design package;
 
   
Technique service on-the-spot
 
Contract Price
   
Party A would pay Party B RMB 17,900,000 as the sum of the service contract.
 
   
20% of the amount would be paid by Party A no longer than 15 days since the contract was signed.
 
   
10% of the amount would be paid by Party A in 2 weeks after the whole technology design package was delivered by Party B.
 
   
22.5% of the amount would be paid by Party A in 2 weeks after the first notice of sending equipments was send out by Party B.
 
   
17.5% of the amount would be paid by Party A in 2 weeks after the second notice of sending equipments was send out by Party B.
 
   
10% of the amount would be paid by Party A in 2 weeks after the third notice of sending equipments was send out by Party B.
 
   
5% of the amount would be paid by Party A before the starting of the IC reactor and after the IC reactor was installed by Party B.
 
   
5% of the amount would be paid by Party A before the starting of the ANAMMOX reactor and after the ANAMMOX reactor was installed by Party B.
 
   
5% of the amount would be paid by Party A in 2 weeks after the whole system was checked as qualified.
   
5% of the amount would be paid by Party A in 2 months when the quality assurance term was expired.

 

 


 

 
Delivery
   
Delivery Place: Party A’s project scene site.
 
   
Delivery of the technology design package: no longer than 30 days since the contract was signed.
 
   
Delivery of the key equipment: no longer than 90 days since the contract was signed for IC reactor, standpipe, and PLC system; no longer than 180 days since the contract was signed for ANAMMOX reactor; no longer than 240 days since the contract was signed for denitration sand filter.
 
Warranty and Breach of Contract
   
Party B promises that the technology is advanced and well-rounded and the equipments are new and well-qualified. Party B shall offering whole information of the technology.
 
   
Party B promises that their staffs are healthy, experienced and competent. Any lost caused by the mistakes made by Party B’s staff would be totally compensated by Party B.
 
   
Any defects of equipments or materials caused by Party B shall be remedied by Party B.
 
   
Party B should pay 0.5% of the amount of the delayed goods as penalty when the delay of good delivery was caused by Party B.
 
   
Party A should pay 0.5% of the amount of the delayed payment as penalty when the delay of payment was caused by Party B or the delay of good delivery was caused by Party A.
 
   
Party A is entitled to terminate the contract when the delay of good delivery caused by Party B is more than 8 weeks.
 
   
Party B is entitled to terminate the contract when the delay of payment caused by Party A is more than 8 weeks.
 
Function test
   
The function test should be completed no longer than 3 months since the biology project started.
 
Headlines of the articles omitted
   
Force Majeure
 
   
Confidential Clause
 
   
Dispute Settlement
 
   
Miscellaneous
 
   
Effectiveness
 
   
Validity
 
   
Attention