CHANGE ORDER FORM Milestone Payment Adjustments PROJECT NAME:Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 20, 2012CHANGE ORDER NUMBER: CO-00020 DATE OF CHANGE ORDER: January 12, 2016
EX-10.2 3 exhibit102spl2016form10q1s.htm EXHIBIT 10.2 Exhibit
Exhibit 10.2
CHANGE ORDER FORM
Milestone Payment Adjustments
PROJECT NAME: Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 20, 2012 | CHANGE ORDER NUMBER: CO-00020 DATE OF CHANGE ORDER: January 12, 2016 |
The Agreement between the Parties listed above is changed as follows:
1. | The following payment milestones in Attachment C of the Agreement will be amended: |
A. Payment Milestone: 31.01 LNG Train 3 - 50% Complete of Installation of Above Ground Pipe
The milestone is hereby amended by deleting the phrase ‘original budgeted’ and replacing with ‘current forecast’.
B. Payment Milestone: 43.01 Subproject 3 - Finish Installation of Above Ground Pipe
The milestone is hereby amended by deleting the phrase ‘original budgeted’ and replacing with ‘current forecast’.
Adjustment to Contract Price
The original Contract Price was | $ | 3,769,000,000 | |
Net change by previously authorized Change Orders (#0001-00019) | $ | 31,299,776 | |
The Contract Price prior to this Change Order was | $ | 380,299,776 | |
The Contract Price will be (increased) by this Change Order in the amount of | $ | — | |
The new Contract Price including this Change Order will be | $ | 3,800,299,776 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): No impact to Project Schedule.
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)
Adjustment to Payment Schedule: No
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ Ed Lehotsky | /s/ Dena Volovar | |
Owner | Contractor | |
Ed Lehotsky | Dena Volovar | |
Name | Name | |
VP LNG Projects | Project Manager | |
Title | Title | |
January 25, 2016 | January 12, 2016 | |
Date of Signing | Date of Signing |