CHANGE ORDER FORM
Milestone Payment Adjustments

PROJECT NAME:  Sabine Pass LNG Stage 2 Liquefaction Facility

OWNER: Sabine Pass Liquefaction, LLC

CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.

DATE OF AGREEMENT: December 20, 2012
CHANGE ORDER NUMBER: CO-00020

DATE OF CHANGE ORDER: January 12, 2016


The Agreement between the Parties listed above is changed as follows:

1.
The following payment milestones in Attachment C of the Agreement will be amended:

A. Payment Milestone: 31.01 LNG Train 3 - 50% Complete of Installation of Above Ground Pipe

The milestone is hereby amended by deleting the phrase ‘original budgeted’ and replacing with ‘current forecast’.

B. Payment Milestone: 43.01 Subproject 3 - Finish Installation of Above Ground Pipe

The milestone is hereby amended by deleting the phrase ‘original budgeted’ and replacing with ‘current forecast’.


Adjustment to Contract Price
The original Contract Price was
$
3,769,000,000

Net change by previously authorized Change Orders (#0001-00019)
$
31,299,776

The Contract Price prior to this Change Order was
$
380,299,776

The Contract Price will be (increased) by this Change Order in the amount of
$

The new Contract Price including this Change Order will be
$
3,800,299,776


Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): No impact to Project Schedule.


Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)


Adjustment to Payment Schedule: No

Adjustment to Minimum Acceptance Criteria: N/A

Adjustment to Performance Guarantees: N/A

Adjustment to Design Basis: N/A

Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A









Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner


[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner

Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.

/s/ Ed Lehotsky
 
/s/ Dena Volovar
Owner
 
Contractor
Ed Lehotsky
 
Dena Volovar
Name
 
Name
VP LNG Projects
 
Project Manager
Title
 
Title
January 25, 2016
 
January 12, 2016
Date of Signing
 
Date of Signing