CHANGE ORDER FORM April Site Closure for Cheniere Celebration PROJECT NAME:Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 11, 2011CHANGE ORDER NUMBER: CO-00045 DATE OF CHANGE ORDER: April 4, 2016
EX-10.2 2 exhibit102spl2016form10-q2.htm EXHIBIT 10.2 Exhibit
Exhibit 10.2
CHANGE ORDER FORM
April Site Closure for Cheniere Celebration
PROJECT NAME: Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 11, 2011 | CHANGE ORDER NUMBER: CO-00045 DATE OF CHANGE ORDER: April 4, 2016 |
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. | Parties agree Bechtel will temporarily close SPL Site on April 25, 2016 in observance of Sabine Pass LNG Opening Celebration Day. No construction activities on Site will be performed on this day. |
2. | The overall cost breakdown is detailed in Exhibit A. |
3. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 3,900,000,000 | |
Net change by previously authorized Change Orders (#0001-00044) | $ | 215,447,859 | |
The Contract Price prior to this Change Order was | $ | 4,115,447,859 | |
The Contract Price will be (increased) by this Change Order in the amount of | $ | 1,325,996 | |
The new Contract Price including this Change Order will be | $ | 4,116,773,855 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): No Project Schedule dates will be modified.
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)
Adjustment to Payment Schedule: Yes. See Exhibits A and B
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ Ed Lehotsky | /s/ Dena Volovar | |
Owner | Contractor | |
Ed Lehotsky | Dena Volovar | |
Name | Name | |
VP LNG Projects | Project Manager | |
Title | Title | |
April 27, 2016 | April 5, 2016 | |
Date of Signing | Date of Signing |
CHANGE ORDER FORM
PROJECT NAME: Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 11, 2011 | CHANGE ORDER NUMBER: CO-00046 DATE OF CHANGE ORDER: May 17, 2016 |
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
The Parties agree to amend the required date for the performance of the Ship Loading Time Test.
Adjustment to Contract Price
The original Contract Price was | $ | 3,900,000,000 | |
Net change by previously authorized Change Orders (#0001-00045) | $ | 216,773,855 | |
The Contract Price prior to this Change Order was | $ | 4,116,773,855 | |
The Contract Price will be (increased) by this Change Order in the amount of | $ | Unchanged | |
The new Contract Price including this Change Order will be | $ | 4,116,773,855 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)
Adjustment to Payment Schedule: N/A
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: See Exhibit 1.
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ SB Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ Ed Lehotsky | /s/ Sergio Buoncristiano | |
Owner | Contractor | |
Ed Lehotsky | Sergio Buoncristiano | |
Name | Name | |
SVP LNG E&C | Sr. Vice President | |
Title | Title | |
May 26, 2016 | May 25, 2016 | |
Date of Signing | Date of Signing |
CHANGE ORDER FORM
Re-Orientation of PSV Bypass Valves
PROJECT NAME: Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 11, 2011 | CHANGE ORDER NUMBER: CO-00047 DATE OF CHANGE ORDER: May 25, 2016 |
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will modify the current PSV bypass valve orientation on Subproject 2 so that the cavity relief vents of the PSV bypass valves are on the high pressure side of the valves. This Change Order includes engineering hours to revise P&IDs and Isometric drawings for Subproject 1 and Subproject 2. Subproject 1 field reorientation will be performed by SPL at a future date. |
2. | The following payment milestones in Attachment C of the Agreement will be amended: |
a. | Payment Milestone: 55.02 Progress report or equivalent shows 90% complete of original budget quantity earned. |
The milestone is hereby amended by deleting the phrase ‘original budgeted’ and replacing with ‘current forecast’.
3. | The overall cost breakdown for this Change Order is detailed in Exhibit A. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 3,900,000,000 | |
Net change by previously authorized Change Orders (#0001-00046) | $ | 216,773,855 | |
The Contract Price prior to this Change Order was | $ | 4,116,773,855 | |
The Contract Price will be (increased) by this Change Order in the amount of | $ | 12,824 | |
The new Contract Price including this Change Order will be | $ | 4,116,786,679 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)
Adjustment to Payment Schedule: Yes. See Exhibit B
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ Ed Lehotsky | /s/ Dena Volovar | |
Owner | Contractor | |
Ed Lehotsky | Dena Volovar | |
Name | Name | |
SVP LNG E&C | Principal Vice President | |
Title | Title | |
June 16, 2016 | May 25, 2016 | |
Date of Signing | Date of Signing |