CHANGE ORDER FORM Addition of Check Valves to Condensate Lines and Change of Tie-in Point
Exhibit 10.59
CHANGE ORDER FORM
Addition of Check Valves to Condensate Lines and Change of Tie-in Point
PROJECT NAME: Sabine Pass LNG Stage 3 Liquefaction Facility
OWNER: Sabine Pass Liquefaction, LLC
CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.
DATE OF AGREEMENT: May 4, 2015 | CHANGE ORDER NUMBER: CO-00012
DATE OF CHANGE ORDER: September 12, 2016 |
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will design, procure and install a check valve on the condensate line. Exhibit A of this Change Order depicts this change. |
2. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will reroute the condensate line, through an existing valve, to a new tie-in location. Exhibit B of this Change Order depicts this change. |
3. | The cost breakdown for this Change Order is detailed in Exhibit C. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit D of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 2,987,000,000 | ||
Net change by previously authorized Change Orders (#0001-00011) | $ | (791,828 | ) | |
The Contract Price prior to this Change Order was | $ | 2,986,208,172 | ||
The Contract Price will be changed by this Change Order in the amount of | $ | (327,860 | ) | |
The new Contract Price including this Change Order will be | $ | 2,985,880,312 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary). N/A
Adjustment to Payment Schedule: Yes. See Exhibit D.
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement:
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties duly authorized representatives.
/s/ Ed Lehotsky | /s/ Dena Volovar | |||||
Owner | Contractor | |||||
Ed Lehotsky | Dena Volovar | |||||
Name | Name | |||||
SVP LNG E&C | Principal Vice President | |||||
Title | Title | |||||
October 5, 2016 | September 12, 2016 | |||||
Date of Signing | Date of Signing |
CHANGE ORDER FORM
LNG Rundown Line Reroute
PROJECT NAME: Sabine Pass LNG Stage 3 Liquefaction Facility
OWNER: Sabine Pass Liquefaction, LLC
CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.
DATE OF AGREEMENT: May 4, 2015 | CHANGE ORDER NUMBER: CO-00013
DATE OF CHANGE ORDER: September 12, 2016 |
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will reroute portions of the 24-inch LNG rundown line, 2-inch vent line, and 2-inch blowdown line. This Change Order also includes installation of associated piling and three monorails without any lifting devices. Exhibit A of this Change Order depicts these changes. |
2. | The cost breakdown for this Change Order is detailed in Exhibit B. |
3. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit C of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 2,987,000,000 | ||
Net change by previously authorized Change Orders (#0001-00012) | $ | (1,119,688 | ) | |
The Contract Price prior to this Change Order was | $ | 2,985,880,312 | ||
The Contract Price will be changed by this Change Order in the amount of | $ | 772,191 | ||
The new Contract Price including this Change Order will be | $ | 2,986,652,503 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary). N/A
Adjustment to Payment Schedule: Yes. See Exhibit C.
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement:
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties duly authorized representatives.
/s/ Ed Lehotsky | /s/ Dena Volovar | |||||
Owner | Contractor | |||||
Ed Lehotsky | Dena Volovar | |||||
Name | Name | |||||
SVP LNG E&C | Principal Vice President | |||||
Title | Title | |||||
October 5, 2016 | September 12, 2016 | |||||
Date of Signing | Date of Signing |
CHANGE ORDER FORM
Pre-EPC HAZOP Action Item Closure
PROJECT NAME: Sabine Pass LNG Stage 3 Liquefaction Facility
OWNER: Sabine Pass Liquefaction, LLC
CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.
DATE OF AGREEMENT: May 4, 2015 | CHANGE ORDER NUMBER: CO-00014
DATE OF CHANGE ORDER: September 27, 2016 |
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will resolve the Action Items identified in the HAZOP Study that was conducted prior to NTP. The Action Items are listed in Exhibit A of this Change Order. |
2. | The cost breakdown for this Change Order is detailed in Exhibit B. |
3. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit C of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 2,987,000,000 | ||
Net change by previously authorized Change Orders (#0001-00013) | $ | (347,497 | ) | |
The Contract Price prior to this Change Order was | $ | 2,986,652,503 | ||
The Contract Price will be changed by this Change Order in the amount of | $ | 8,981,813 | ||
The new Contract Price including this Change Order will be | $ | 2,995,634,316 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary). N/A
Adjustment to Payment Schedule: Yes. See Exhibit C.
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement:
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties duly authorized representatives.
/s/ Ed Lehotsky | /s/ Dena Volovar | |||||
Owner | Contractor | |||||
Ed Lehotsky | Dena Volovar | |||||
Name | Name | |||||
SVP LNG E&C | Principal Vice President | |||||
Title | Title | |||||
October 10, 2016 | September 28, 2016 | |||||
Date of Signing | Date of Signing |
CHANGE ORDER FORM
Study for Enclosed Ground Flare and Process Flare
PROJECT NAME: Sabine Pass LNG Stage 3 Liquefaction Facility
OWNER: Sabine Pass Liquefaction, LLC
CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.
DATE OF AGREEMENT: May 4, 2015 | CHANGE ORDER NUMBER: CO-00015
DATE OF CHANGE ORDER: September 27, 2016 |
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will conduct a preliminary study to evaluate the cost and schedule impacts of modifying the planned process flares to include high pressure air assist (HPAA) and to add a totally enclosed ground flare (TEGF). |
2. | The cost breakdown for this Change Order is detailed in Exhibit A. |
3. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 2,987,000,000 | ||
Net change by previously authorized Change Orders (#0001-00014) | $ | 8,634,316 | ||
The Contract Price prior to this Change Order was | $ | 2,995,634,316 | ||
The Contract Price will be changed by this Change Order in the amount of | $ | 1,363,835 | ||
The new Contract Price including this Change Order will be | $ | 2,996,998,151 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A based on the study scope of this Change Order
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary). N/A
Adjustment to Payment Schedule: Yes. See Exhibit B.
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement:
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties duly authorized representatives.
/s/ Ed Lehotsky | /s/ Dena Volovar | |||||
Owner | Contractor | |||||
Ed Lehotsky | Dena Volovar | |||||
Name | Name | |||||
SVP LNG E&C | Principal Vice President | |||||
Title | Title | |||||
October 10, 2016 | September 28, 2016 | |||||
Date of Signing | Date of Signing |
CHANGE ORDER FORM
Upgrades to Gas Turbine Generators
PROJECT NAME: Sabine Pass LNG Stage 3 Liquefaction Facility
OWNER: Sabine Pass Liquefaction, LLC
CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.
DATE OF AGREEMENT: May 4, 2015
| CHANGE ORDER NUMBER: CO-00016
DATE OF CHANGE ORDER: October 19, 2016 |
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will update the Stage 3 Gas Turbine Generators to ensure synchronization with existing systems. The following hardware and software updates are needed to make the Stage 3 GTGs compatible with Stages 1 and 2 with accompanying details in Exhibit A of this Change Order: |
a. | Woodward DSLA-2 (Second Generation Digital Synchronizer and Load Sharing Control); |
b. | MicroNet Plus hardware and software; |
c. | Triple Block and Bleed Arrangement with Bottle Test and Installation of CO2 Bottle Weight System. |
2. | The Existing & Stages 1 and 2 Liquefaction Facility Labor Provisional Sum value was Fifty Million, Three Hundred Sixteen Thousand, Six Hundred Eighty-Two U.S. Dollars (U.S. $50,316,682) and Three Hundred Sixty Thousand, One Hundred Twelve (360,112) hours. These values will be amended and the new values shall be Fifty Million, Five Hundred Fifty Million, Fifty-Three U.S. Dollars (U.S. $50,550,053) and Three Hundred Sixty-One Thousand, Nine Hundred Forty-Six (361,946) hours. |
a. | The Aggregate Provisional Sum specified in Article 7.1A of the Agreement prior to this Change Order was $300,491,679. This value will be increased by $233,371 and the new value shall be $300,725,050. |
3. | The cost breakdown for this Change Order is detailed in Exhibit B. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit C of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 2,987,000,000 | ||
Net change by previously authorized Change Orders (#0001-00015) | $ | 9,998,151 | ||
The Contract Price prior to this Change Order was | $ | 2,996,998,151 | ||
The Contract Price will be changed by this Change Order in the amount of | $ | 2,703,387 | ||
The new Contract Price including this Change Order will be | $ | 2,999,701,538 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary). N/A
Adjustment to Payment Schedule: Yes. See Exhibit B.
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement:
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties duly authorized representatives.
/s/ Ed Lehotsky | /s/ Dena Volovar | |||||
Owner | Contractor | |||||
Ed Lehotsky | Dena Volovar | |||||
Name | Name | |||||
SVP LNG E&C | Principal Vice President | |||||
Title | Title | |||||
November 1, 2016 | October 19, 2016 | |||||
Date of Signing | Date of Signing |
CHANGE ORDER FORM
Site Drainage Design Change: Temporary Drainage Implementation
PROJECT NAME: Sabine Pass LNG Stage 3 Liquefaction Facility
OWNER: Sabine Pass Liquefaction, LLC
CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.
DATE OF AGREEMENT: May 4, 2015 | CHANGE ORDER NUMBER: CO-00017
DATE OF CHANGE ORDER: December 1, 2016 |
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will modify the original drainage plan to move the drainage outfall to the Southeast side of the Site. As the permit to construct the new outfall will not be available for 9+ months, a temporary drainage system is necessary to control water during the interim period. The key items for the Stage 3 Temporary Drainage Plan are listed as follows: |
a. | The North Outfall and temporary Detention Pond to be designed to handle the flow for a 10-year storm. |
b. | The ditches, culverts, etc. to be redesigned to direct the flow to the temporary outfall in order to handle the flow for a 10-year storm. |
c. | Sump pumps to be provided (including temporary power) to pump the flow from the Detention Pond to the temporary North Outfall. |
d. | Twelve (12) months of temporary drainage operation is assumed. |
e. | Removal of original drainage quantities will be addressed in a future Change Order. |
For clarity, these changes are depicted in Exhibit A of this Change Order.
2. | Costs of soil stabilization and costs related to the permanent drainage design and installation are not included in this Change Order. |
3. | The cost breakdown for this Change Order is detailed in Exhibit B. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit C of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 2,987,000,000 | ||
Net change by previously authorized Change Orders (#0001-00016) | $ | 12,701,538 | ||
The Contract Price prior to this Change Order was | $ | 2,999,701,538 | ||
The Contract Price will be changed by this Change Order in the amount of | $ | 5,528,732 | ||
The new Contract Price including this Change Order will be | $ | 3,005,230,270 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary). N/A
Adjustment to Payment Schedule: Yes. See Exhibit C.
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement:
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties duly authorized representatives.
/s/ Ed Lehotsky | /s/ Dena Volovar | |||||
Owner | Contractor | |||||
Ed Lehotsky | Dena Volovar | |||||
Name | Name | |||||
SVP LNG E&C | Principal Vice President | |||||
Title | Title | |||||
August 15, 2016 | December 1, 2016 | |||||
Date of Signing | Date of Signing |