- Change order (Filed With SEC on May 3, 2024)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 8, 2018, by... (Filed With SEC on November 2, 2023)
- Letter agreement regarding change from LIBOR to SOFR, dated May 18, 2023, to LNG Sale and Purchase Agreement, dated January 25, 2012, between the Company and BG Gulf Coast LNG,... (Filed With SEC on August 3, 2023)
- Letter agreement regarding change from LIBOR to SOFR, dated June 16, 2023, to LNG Sale and Purchase Agreement, dated December 11, 2011, between the Company and GAIL (India)... (Filed With SEC on August 3, 2023)
- Letter agreement regarding change from LIBOR to SOFR, dated June 30, 2023, to LNG Sale and Purchase Agreement, dated January 30, 2012, between the Company and Korea Gas... (Filed With SEC on August 3, 2023)
- Letter agreement regarding change from LIBOR to SOFR, dated June 8, 2023, to LNG Sale and Purchase Agreement, dated November 21, 2011, between the Company and Naturgy LNG GOM,... (Filed With SEC on August 3, 2023)
- Letter agreement regarding change from LIBOR to SOFR, dated June 26, 2023, to Amended and Restated LNG Sale and Purchase Agreement (FOB) between the Company and Cheniere Marketing... (Filed With SEC on August 3, 2023)
- Fourth Amended and Restated Common Terms Agreement, among the Company, as borrower, the Secured Debt Holder Group Representatives party thereto, the Secured Hedge Representatives... (Filed With SEC on July 13, 2023)
- Senior Revolving Credit and Guaranty Agreement, among the Company, as borrower, certain subsidiaries of the Company, The Bank of Nova Scotia, as Senior Facility Agent, Socit... (Filed With SEC on July 13, 2023)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November (Filed With SEC on May 2, 2023)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on February 23, 2023)
- Registration Rights Agreement, dated as of November 29, 2022, between Sabine Pass Liquefaction, LLC and Goldman Sachs & Co. LLC (Filed With SEC on November 29, 2022)
- Twelfth Supplemental Indenture, dated as of November 29, 2022, between Sabine Pass Liquefaction, LLC and The Bank of New York Mellon, as Trustee under the Indenture (Filed With SEC on November 29, 2022)
- Purchase Agreement, dated as of November 14, 2022, between Sabine Pass Liquefaction, LLC and Goldman Sachs & Co. LLC (Filed With SEC on November 15, 2022)
- LNG Sale and Purchase Agreement (Filed With SEC on November 3, 2022)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on November 3, 2022)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on August 4, 2022)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on May 4, 2022)
- Letter Agreement, dated November 24, 2021, regarding the Amended and Restated LNG Sale and Purchase Agreement (FOB), dated August 5, 2014, between Sabine Pass Liquefaction, LLC... (Filed With SEC on November 26, 2021)
- Letter agreement, dated November (Filed With SEC on November 4, 2021)
- First Amendment to Third Amended and Restated Common Terms Agreement, dated as of July 26, 2021, among the Company, as borrower, the Secured Debt Holder Group Representatives... (Filed With SEC on November 4, 2021)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on November 4, 2021)
- Letter Agreement, dated August (Filed With SEC on August 5, 2021)
- Letter Agreement, dated August (Filed With SEC on August 5, 2021)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on August 5, 2021)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on May 4, 2021)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on February 24, 2021)
- Letter Agreement, dated February 23, 2021, regarding the Amended and Restated LNG Sale and Purchase Agreement (FOB), dated August 5, 2014, between the Company and Cheniere... (Filed With SEC on February 24, 2021)
- Letter Agreement, dated December 9, 2020, regarding the Amended and Restated LNG Sale and Purchase Agreement (FOB), dated August 5, 2014, between Sabine Pass Liquefaction, LLC and... (Filed With SEC on December 10, 2020)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on November 6, 2020)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on August 6, 2020)
- Registration Rights Agreement, dated as of May 8, 2020, between Sabine Pass Liquefaction, LLC and Morgan Stanley & Co. LLC (Filed With SEC on May 8, 2020)
- Eleventh Supplemental Indenture, dated as of May 8, 2020, between Sabine Pass Liquefaction, LLC and The Bank of New York Mellon, as Trustee under the Indenture (Filed With SEC on May 8, 2020)
- Purchase Agreement, dated as of May 5, 2020, between Sabine Pass Liquefaction, LLC and Morgan Stanley & Co. LLC (Filed With SEC on May 8, 2020)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on April 30, 2020)
- Third Amended and Restated Common Terms Agreement, among the Company, as borrower, the Secured Debt Holder Group Representatives party thereto, the Secured Hedge Representatives... (Filed With SEC on March 23, 2020)
- Third Amended and Restated Accounts Agreement, among the Company, certain subsidiaries of the Company, Socit Gnrale, as the Common Security Trustee, and Citibank, N.A. as the... (Filed With SEC on March 23, 2020)
- Working Capital Revolving Credit and Letter of Credit Reimbursement Agreement, among the Company, as borrower, certain subsidiaries of the Company, The Bank of Nova Scotia, as... (Filed With SEC on March 23, 2020)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on February 25, 2020)
- Letter Agreement regarding the Base SPA, dated December 23, 2019, amending the Amended and Restated LNG Sale and Purchase Agreement (FOB), dated August 5, 2014, between Sabine... (Filed With SEC on December 23, 2019)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on November 1, 2019)
- Amended and Restated Senior Working Capital Revolving Credit and Letter of Credit Reimbursement Agreement, dated September 4, 2015, as amended by (a) Third Omnibus Amendment,... (Filed With SEC on August 8, 2019)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by... (Filed With SEC on August 8, 2019)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 2 Liquefaction Facility, dated December 20, 2012, by... (Filed With SEC on August 8, 2019)
- Amendment No. 1 of Amended and Restated LNG Sale and Purchase Agreement, dated May 3, 2019, by and between the Company and Cheniere Marketing International LLP (Filed With SEC on May 9, 2019)
- Letter Agreement regarding the Base SPA, dated May 3, 2019, amending the Amended and Restated LNG Sale and Purchase Agreement (FOB), dated August 5, 2014, between the Company and... (Filed With SEC on May 9, 2019)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 3 Liquefaction Facility, dated as of May 4, 2015,... (Filed With SEC on February 26, 2019)
- Fourth Omnibus Amendment, dated as of September 17, 2018, to (a) the Second Amended and Restated Common Terms Agreement, dated as of June 30, 2015, by and among the Company, as... (Filed With SEC on November 8, 2018)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 3 Liquefaction Facility, dated as of May 4, 2015,... (Filed With SEC on August 9, 2018)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 3 Liquefaction Facility, dated as of May 4, 2015,... (Filed With SEC on May 4, 2018)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 3 Liquefaction Facility, dated as of May 4, 2015,... (Filed With SEC on February 21, 2018)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Liquefaction Facility, dated as of November 11, 2011,... (Filed With SEC on November 9, 2017)
- Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 2 Liquefaction Facility, dated as of December 20,... (Filed With SEC on November 9, 2017)
- Change order to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 3 Liquefaction Facility, dated as of May 4, 2015,... (Filed With SEC on November 9, 2017)
- CHANGE ORDER FORM Stage3 Process Flare Modification (Filed With SEC on June 9, 2017)
- CHANGE ORDER FORM Ingersoll Rand Vendor HAZOP Updates (Filed With SEC on June 9, 2017)
- CHANGE ORDER FORM Process Flare Provisional Sum Closeout (Filed With SEC on June 9, 2017)
- Sabine Pass Liquefaction, LLC (Filed With SEC on February 24, 2017)
- Sabine Pass Liquefaction, LLC (Filed With SEC on February 3, 2017)
- CHANGE ORDER FORM Adjustment (Filed With SEC on February 3, 2017)
- Sabine Pass Liquefaction, LLC (Filed With SEC on February 3, 2017)
- CHANGE ORDER FORM Addition of Check Valves to Condensate Lines and Change of Tie-in Point (Filed With SEC on February 3, 2017)
- CHANGE ORDER FORM Professional Services for Control System Changes Post TCCC (Filed With SEC on February 3, 2017)
- SECOND OMNIBUS AMENDMENT AND WAIVER (Filed With SEC on February 3, 2017)
- AMENDMENT TO THE COMMON TERMS AGREEMENT (Filed With SEC on February 3, 2017)
- CHANGE ORDER FORM N2 Supply for High Pressure Tightness Test During Commissioning and Startup PROJECT NAME:Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass Liquefaction,... (Filed With SEC on November 3, 2016)
- CHANGE ORDER FORM Additional Support for FERC Document Requests PROJECT NAME:Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel... (Filed With SEC on November 3, 2016)
- CHANGE ORDER FORM Site Drainage Design Change: Professional Service Hours PROJECT NAME:Sabine Pass LNG Stage 3 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC... (Filed With SEC on November 3, 2016)
- CHANGE ORDER FORM April Site Closure for Cheniere Celebration PROJECT NAME:Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas... (Filed With SEC on August 9, 2016)
- CHANGE ORDER FORM Smokeless Flare Modification Study PROJECT NAME:Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas... (Filed With SEC on August 9, 2016)
- CHANGE ORDER FORM Performance and Attendance Bonus (PAB) Incentive Program Provisional Sum PROJECT NAME:Sabine Pass LNG Stage 3 Liquefaction Facility OWNER: Sabine Pass... (Filed With SEC on August 9, 2016)
- CHANGE ORDER FORM DOE Regulation Change Impacts, RECON Schedule Change, Addition of Dry Flare Connection, Fuel Gas Supply Transfer to Train 5 and East Meter Fuel Gas PROJECT... (Filed With SEC on May 5, 2016)
- CHANGE ORDER FORM Potable Water Bypass Line and Pipe Installation Tie-In at 135-A Metering Station PROJECT NAME:Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass... (Filed With SEC on May 5, 2016)
- CHANGE ORDER FORM Milestone Payment Adjustments PROJECT NAME:Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and... (Filed With SEC on May 5, 2016)
- CHANGE ORDER FORM Perimeter Fencing Scope Removal, East Meter Piping Scope Change, Additional Bathroom Facilities (Filed With SEC on February 19, 2016)
- CHANGE ORDER FORM Platform Design Modifications, Compressor Oil Fills, Additional Building Modifications PROJECT NAME:Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass... (Filed With SEC on February 19, 2016)
- CHANGE ORDER FORM Platform Design Modifications, Compressor Oil Fills, Additional Building Modifications (Filed With SEC on November 25, 2015)
- CHANGE ORDER FORM East Meter Piping Tie-ins (Filed With SEC on October 30, 2015)
- CHANGE ORDER FORM Credit to EPC Contract Value for TSA Work (Filed With SEC on October 30, 2015)
- SCHEDULE D-1 CHANGE ORDER FORM (for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C) PROJECT NAME:Sabine Pass LNG Stage 3... (Filed With SEC on July 30, 2015)
- CHANGE ORDER FORM Permanent Restroom Trailers and Installation of Tie-In for GTG Fuel Gas Interconnect PROJECT NAME:Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Sabine... (Filed With SEC on July 30, 2015)
- CHANGE ORDER FORM Additional Building Utility Tie-in Packages and Fire and Gas Modifications PROJECT NAME:Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass Liquefaction,... (Filed With SEC on July 30, 2015)
- CHANGE ORDER FORM Increase to Existing Facility Labor Provisional Sum and Decrease to Sales and Use Tax Provisional Sum PROJECT NAME:Sabine Pass LNG Liquefaction Facility OWNER:... (Filed With SEC on April 30, 2015)
- CHANGE ORDER FORM Louisiana Sales and Use Tax Provisional Sum Adjustment PROJECT NAME:Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC... (Filed With SEC on April 30, 2015)
- CHANGE ORDER FORM Performance and Attendance Bonus (PAB) Incentive Program Provisional Sum PROJECT NAME:Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Sabine Pass... (Filed With SEC on February 20, 2015)
- CHANGE ORDER FORM Performance and Attendance Bonus (PAB) Incentive Program Provisional Sum PROJECT NAME:Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC... (Filed With SEC on February 20, 2015)
- CHANGE ORDER FORM Additional 13.8kv Circuit Breakers and Misc. Items (Filed With SEC on August 26, 2014)
- CHANGE ORDER FORM Future Tie-Ins and Jeff Davis Invoices (Filed With SEC on August 26, 2014)
- CHANGE ORDER FORM Resolution of FERC Open Items, Additional FERC Support Hours and Greenfield/Brownfield Milestone Adjustment PROJECT NAME:Sabine Pass LNG Liquefaction Facility... (Filed With SEC on July 31, 2014)
- CHANGE ORDER FORM Intra-Plant Feed Gas Header and Jefferson Davis Electrical Distribution PROJECT NAME:Sabine Pass LNG Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC... (Filed With SEC on May 1, 2014)
- CHANGE ORDER FORM Insurance Provisional Sum Adjustment PROJECT NAME:Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas... (Filed With SEC on May 1, 2014)
- TAX SHARING AGREEMENT Among and Between Cheniere Energy, Inc. AND Sabine PassLiquefaction, LLC Dated as of August 9, 2012 TAX SHARING AGREEMENT (Filed With SEC on November 15, 2013)