Change Order No. 02 to Tenant Improvements Contract between Adicet Therapeutics, CP Construction, and Form4 Architecture
This change order amends the original tenant improvements contract dated April 2, 2021, between Adicet Therapeutics (owner), CP Construction (contractor), and Form4 Architecture (architect). It authorizes additional work for vivarium modifications, including demolition, electrical, HVAC, plumbing, fire alarm, fire sprinklers, framing, drywall, taping, and painting, totaling $42,350. The contract sum increases to $13,804,450, and the project timeline is extended by 30 days. The change order is valid only when signed by all parties.
Document G701
Change Order
|
| Change Order Number: 02 |
|
| |
Project: Adicet Therapeutics 1000 Bridge Parkway Redwood City, CA 94065 |
| Date: 7-Feb-22
Architect's Project No: |
|
Owner
Architect |
□
□ |
|
|
|
|
|
|
To Contractor: (Name and Address CP Construction a Division of CP Enterprises Newark, CA 94560 |
| Contract Date: 2 April 2021 Contract For: Tenant Improvements |
|
Contractor
Field
Other |
□
□
□ |
The Contract is changed as follows:
(Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives)
Vivarium Modifications
Per email correspondence with Charlie Penner on 2/3/22 for the following work: |
|
|
Demo |
| $ 2,500.00 |
Electrical |
| $ 8,000.00 |
HVAC & Plumbing |
| $ 8,500.00 |
Fire Alarm |
| $ 2,000.00 |
Fire Sprinklers |
| $ 3,000.00 |
Frame & Drywall |
| $ 10,000.00 |
Tape & Paint |
| $ 4,500.00 |
Subtotal |
| $ 38,500.00 |
10% Profit, Overhead & Insurance |
| $ 3,850.00 |
Total |
| $ 42,350.00 |
The original Contract Sum was |
| $ 13,625,700.00 |
The net change by previously authorized Change Orders |
| $ 136,400.00 |
The Contract Sum prior to this Change Order was |
| $ 13,762,100.00 |
The Contract Sum will be increased by this Change Order in the amount of |
| $ 42,350.00 |
The new Contract Sum including this Change Order will be |
| $ 13,804,450.00 |
The Contract will be increased by 30 days |
|
|
The date of Substantial Completion as of the date of this Change Order therefore is |
|
|
(Note: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.)
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
Form4 Architecture, Inc. |
| CP Construction |
| Adicet Therapeutics, Inc. |
ARCHITECT (Firm Name) |
| CONTRACTOR (Firm Name) |
| OWNER (Firm Name) |
|
|
|
|
|
120 2nd St# 2. San Francisco, CA 94105 |
| 6662 Mayhews Landing Rd. Newark, 94560 |
| 200 Constitution Dr. Menlo Park, CA 94025 |
Address |
| Address |
| Address |
|
|
|
|
|
/s/ Paul Ferro |
| /s/ Leslie Hellewell |
| /s/ Chen Schor |
By (Signature) |
| By (Signature) |
| By (Signature) |
|
|
|
|
|
Paul Ferro |
| Leslie Hellewell |
| Chen Schor |
Typed Name |
| Typed Name |
| Typed Name |
|
|
|
|
|
March 2, 2022 |
| February 7, 2022 |
| March 18, 2022 |
Date |
| Date |
| Date |
|
|
|
|
|