Change Order No. 1, dated September 23, 2021, by and between Adicet Therapeutics, Inc. and CP Enterprises, Inc. d/b/a CP Construction

EX-10.1 2 acet-ex10_1.htm EX-10.1 EX-10.1

Document G701

Change Order

 

 

 

 

Change Order Number: 01

 

 

Project: Adicet Therapeutics

1000 Bridge Parkway

Redwood City, CA 94065

 

Date: 21-Sep-21

 

Architect's Project No:

 

 

Owner

 

Architect

 

 

 

 

 

 

 

 

To Contractor: (Name and Address

CP Construction

a Division of CP Enterprises

Newark, CA 94560

 

Contract Date: 2 April 2021

Contract For: Tenant Improvements

 

 

Contractor

 

Field

 

Other

 

 

 

The Contract is changed as follows:

(Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives)

Pressurized Change

 

Per Western Allied and Adicet email dated 8/23/21 for the following work:

 

 

 

Demolition of Installed Duet

 

 

Upsizing (4) Evs

 

 

Upsize exhaust duct runs

 

 

Upsize supply duct run

 

 

Upsize (9) grilles

 

 

Subtotal

 

$ 124,000.00

10% Profit, Overhead & Insurance

 

$ 12,400.00

Total

 

$ 136,400.00

 


The original Contract Sum was

 

$ 13,625,700.00

The net change by previously authorized Change Orders

 

$ 0.00

The Contract Sum prior to this Change Order was

 

$ 13,625,700.00

The Contract Sum will be increased by this Change Order in the amount of

 

$ 136,400.00

The new Contract Sum including this Change Order will be

 

$ 13,762,100.00

The Contract will be unchanged by 0 days

 

 

The date of Substantial Completion as of the date of this Change Order therefore is

 

 

 


 

(Note: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.)

 

NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.

 

Form4 Architecture, Inc.

 

CP Construction

 

Adicet Therapeutics, Inc.

ARCHITECT (Firm Name)

 

CONTRACTOR (Firm Name)

 

OWNER (Firm Name)

 

 

 

 

 

120 2nd St# 2. San Francisco, CA 94105

 

6662 Mayhews Landing Rd. Newark, 94560

 

200 Constitution Dr. Menlo Park, CA 94025

Address

 

Address

 

Address

 

 

 

 

 

/s/ Paul Ferro

 

/s/ Leslie Hellewell

 

/s/ Charlie Penner

By (Signature)

 

By (Signature)

 

By (Signature)

 

 

 

 

 

Paul Ferro

 

Leslie Hellewell

 

Charlie Penner

Typed Name

 

Typed Name

 

Typed Name

 

 

 

 

 

September 23, 2021

 

September 21, 2021

 

September 22, 2021

Date

 

Date

 

Date