Change Order No. 003 to Hard Rock Hotel & Casino Construction Contract between Premier Entertainment Biloxi LLC, Premier Finance Biloxi Corp, Roy Anderson Corp, and Paul Steelman Design Group

Summary

This change order amends the construction contract for the Hard Rock Hotel & Casino in Biloxi, Mississippi, between Premier Entertainment Biloxi LLC, Premier Finance Biloxi Corp, Roy Anderson Corp, and Paul Steelman Design Group. It adds $999,393 to the contract for the build-out of the Ruth's Chris tenant space, specifying included and excluded work. The contract sum increases to $89,750,270, with no change to the completion date. The change order is effective once signed by all parties.

EX-2.2 3 a05-6104_1ex2d2.htm EX-2.2

EXHIBIT 2.2

 

AIA Document ###-###-####

Ownerý

Change Order

Architectý

 

Contractorý

 

Fieldý

 

Othero


PROJECT (Name and address)

CHANGE ORDER NUMBER:

003

 

HARD ROCK HOTEL & CASINO

 

777 BEACH BOULEVARD

DATE:

March 29, 2005

 

BILOXI, MS 39530

 

 

TO CONTRACTOR (Name and address)

ARCHITECT’S PROJECT NO:

23020

 

ROY ANDERSON CORP

CONTRACT DATE:

December 24, 2003

 

PO BOX 2

CONTRACT FOR

Hard Rock Construction

 

GULFPORT, MS 39502

 


THE CONTRACT IS CHANGED AS FOLLOWS

 

 

 1  Ruth's Chris Tenant space Build Out

999,393

 

 The scope of this project shall include drawings and specification as listed below:

 

 

 a.  Architecture Drawings - Dated 1/21/05

 

 

  Drawing list: T-1, A-1.0, A-1.1, A-1.2, A-1.3, A-1.4, A-1.5, A-1.6, A-2.0, A-3.0, A-3.1, A-3.2, A-3.3, A-4.0, A-4.1, A-5.0, A-6.0, A-6.1

 

 

 b.  Specification, Dated 1-21-05

 

 

 c.  Electrical requirement - Design Build by Haynes Electric

 

 

 d.  Mechanical - Design Build by Donaghey Mechanical

 

 

 e.  Exclusion

 

 

  – Furnish and install Kitchen Equipment. Final connection for Electrical and Plumbing are included for all the kitchen equipment.

 

 

  – Furnish and install booth fabric

 

 

  – Furnishing of all Architecture light fixture. Installation of fixtures included

 

 

  – Installation of Exhaust hoods and the stainless steel wall cover

 

 

  – Receiving and installation of all furniture package

 

 

  – Receiving and installation of safe and lobster tank

 

 

  – Furnishing and installation of table padding

 

 

  – Hanging Art Works

 

 

 

Total

999,393

 

 

 

 

The Original Contract Sum Was

$

81,957,183

The Net Change By Previously Authorized Change Orders

$

6,793,694

The Contract Sum Prior To This Change Order Was

$

88,750,877

The Contract Sum Will Be Increased By This Changer Order in the Amount of

$

999,393

The New Contract Sum lncluding This Change Order Will Be

$

89,750,270

 

The Contract Time will be increased by          Zero (0)  Days

 

 

The date of Substantial Completion as of the date of this Change Order therefore is

  8/23/2005

 

 

NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price Which have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive

 

NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER

 

Paul Steelman Design Group

 

Roy Anderson Corp

 

Premier Entertainment Biloxi LLC (Premier)

ARCHITECT (Firm Name)

 

CONTRACTOR (Firm Name)

 

OWNER (Firm Name)

 

 

 

 

Premier Finance Biloxi Corp (PFC)

3330 W Desert Inn Road

 

P.O. Box 2

 

P.O. Box 268

Las Vegas, NV 89102

 

Gulfport, MS 39502

 

Biloxi, MS ###-###-####

ADDRESS

 

ADDRESS

 

ADDRESS

 

 

 

 

 

/s/ Robert Murphy

 

/s/ Meng Chai

 

/s/ Joe Billhimer

BY (Signature)

 

BY (Signature)

 

BY (Signature)

 

 

 

 

For Premier and PFC

Robert Murphy

 

Meng Chai

 

Joe Billhimer

(Type Name)

 

(Type Name)

 

(Type Name)

 

 

 

 

 

03/30/2005

 

3/30/05

 

3/30/05

DATE:

 

DATE:

 

DATE:

 

 

 

 

 


AIA Document ###-###-####. Copyright 1978 and 2001 by The American Institute of Architects.  All rights reserved.  Warning: This AIA Document is protected by the U.S. Copyright Law and International Treaties.  Unauthorized reproduction or distribution of this AIA Document, or any Portion of it, may result in severe civil and criminal penalties and will be prosecuted to the maximum extent possible under the law.  This document was produced by AIA software under Order No 1000097216_1 which expires on 2/8/2005, and is not for resale.