AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

EX-10.3 8 exhibit103.htm EXHIBIT 10.3
Exhibit 10.3
OMB Control No. 1505-0080



AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF                      PAGES
 
1
3
2.  AMENDMENT/MODIFICATION NO.
3.  EFFECTIVE DATE
4.  REQUISITION/PURCHASE REQ. NO.
5.  PROJECT NO. (If applicable)
0012
See Block 16C
W-6-W2-03-TP-R03 036
 
6.  ISSUED BY
CODE
IRS0088
7.  ADMINISTERED BY (If other than Item 6)
 
CODE
 
 
Internal Revenue Service
6009 Oxon Hill Road, Suite 500
Oxon Hill, MD 20745
 
 
 
 
 See Item 6
8.  NAME AND ADDRESS OF CONTRACTOR (No. Street, county, State and ZIP: Code)
 
OFFICIAL PAYMENTS CORPORATION       00051397
2333 SAN RAMON VALLEY BOULEVARD STE# 450
SAN RAMON, CA   ###-###-####
 
OFFICIAL PAYMENTS CORPORATION
 
(x)
9A.  AMENDMENT OF SOLICITATION NO.
 
 
 
9B.  DATED (SEE ITEM 11)
 
 
 
10A.  MODIFICATION OF CONTRACT/ORDER NO.
x
TIRNO-09-C-00019
 
10B.  DATED (SEE ITEM 13)
CODE
FACILITY CODE
 
04/23/2009
11.  THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
  The above numbered solicitation is amended as set forth in Item 14.  The hour and date specified for receipt of Offers  is extended,  is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning _____ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers.  FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATA SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.  If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and data specified.
12.  ACCOUNTING AND APPROPRIATION DATA (If required)
None    Net Increase: $0.00
 
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x)
A.  THIS CHANGE ORDER IS ISSUED PURSUANT TO:  (Specify authority)   THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
 
 
B.  THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
 
C.  THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
X
D.  OTHER Specify type of modification and authority)
Mutual Agreement Between the Parties.
E.  IMPORTANT:  Contractor                                                                          is not,is required to sign this document and return ____ copies to the issuing office.
14.  DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this modification is as follows:
 
1.  Update the Schedule of Performance for Option Year Four.
 
2.  All other terms and conditions remain unchanged.
Except at provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A.  NAME AND TITLE OF SIGNER   (Type or print)
16A.  NAME AND TITLE OF CONTRACTING OFFICER   (Type or print)
Alex P. Hart, President and CEO
 
DIANNE L GOOSBY   202 ###-###-####  /   CONTRACT SPECIALIST
15B.  CONTRACTOR/OFFEROR
15C.  DATE SIGNED
 
16B.  UNITED STATES OF AMERICA
16C.  DATE SIGNED
/s/ Alex P. Hart_____________________________________
(Signature of person authorized to sign)
  05/14/2012
 
BY   __/s/ Dianne L. Goosby_________________________
(Signature of Contracting Officer)
05/15/2012
NSN 7540-01-152-8070                                                                                            30-105                                                              STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE                                                                                                                                                            Computer GeneratedPrescribed by GSA
FAR (48 CFR) 53.243



 

TIRNO-09-C-00019 MOD# 0012


C.1O SCHEDULE OF PERFORMANCE

The Contractor shall provide a project plan (WBS) for system and application
development which shall include the events and dates listed in the chart below. The
dates are tentative and must be coordinated with the COR and IRS's representative
authorized to perform the system security and functional application testing (IV&V). The
timeframes may be modified under the COR's direction and will be updated annually as
contract option years are exercised.

NOTE: All Delivered Transaction Processing Network Documentation must adhere to
the current IRS/Treasury guidance.

Responsible Party
Event
Anticipated Due Dates
Contractor
Provide UNAX briefing documentation
05/12/2012
All
Annual Requirements Review for FS 2013
05/11/2012
Contractor
Provide draft WBS (including requirements, development, testing
and implementation phases)
05/18/2012
IRS
Provide comments on draft WBS
05/25/2012
Contractor
Deliver base lined WBS
06/01/2012
Contractor
Deliver Initial FS 2012 Findings Report
06/01/2012
Contractor
Deliver Initial FS 2012 Marketing Report
06/01/2012
Contractor
Deliver Initial Functional Requirements/User Interface Documentation and workflow schematics; including scripts, web text & screen shots, business rules, etc.
06/29/2012
IRS
Provide initial comments on draft Functional Documentation (iterative process)
07/13/2012
Contractor
Obtain signed contracts with other participating subcontractors, if applicable
07/16/2012
Contractor
Deliver Transaction Processing Network Documentation
07/20/2012
Contractor
Deliver Final Functional Requirements/User Interface Documentation
08/17/2012
Contractor
Deliver Final Test Plans and Test Cases
08/31/2012
Contractor
Begin internal application testing
09/10/2012
Contractor
Deliver FS 2013 Marketing Plan
09/21/2012
IRS
Provide comments on Marketing Plan
09/28/2012
IRS
Provide revised credit card chargeback procedures, if applicable
10/05/2012
Contractor
Complete internal application testing
10/26/2012
Contractor
Begin full circle integrated test with IRS/TFA (subject to change)
11/02/2012
Contractor
Complete full circle test with IRS/TFA (subject to change)
11/16/2012
Contractor
Complete all testing and obtain bulk provider certification from TFA
12/10/2012


Page - 2

TIRNO-09-C-00019 MOD# 0012

Responsible Party
Event
Anticipated Due Dates
Contractor
Implement Electronic Payment Services for FS 2013
01/01/2013
IRS
Provide hyperlink from the IRS web site to the Contractor's Web page
01/08/2013
Contractor
Deliver Supplemental FS 2012 Findings Report
02/01/2013
Contractor
Deliver Supplemental FS 2012 Marketing Report
02/01/2013

Page  - 3