CHANGE ORDER FORM Changes to Outfall (P1, P2, and P5) to LaQuinta Ditch

EX-10.12 14 d322026dex1012.htm EX-10.12 EX-10.12

Exhibit 10.12

*** indicates material has been omitted pursuant to a Confidential Treatment Request filed with the Securities and Exchange Commission. A complete copy of this agreement has been filed separately with the Securities and Exchange Commission.

CHANGE ORDER FORM

Changes to Outfall (P1, P2, and P5) to LaQuinta Ditch

 

PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility

 

OWNER: Corpus Christi Liquefaction, LLC

 

CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.

 

DATE OF AGREEMENT: December 6, 2013

 

  

CHANGE ORDER NUMBER: CO-00026

 

DATE OF CHANGE ORDER: August 31, 2016

 

The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)

 

1. Per Article 6.1.B of the Agreement, Parties agree Contractor will not construct the outfalls P1, P2, and P5 which will take stormflow water to LaQuinta Ditch. Instead, the San Patricio County Drainage District (SPCDD) will hire a subcontractor to excavate, build the headwall, and stabilize the slopes at outfalls P1 and P5 and excavate and stabilize a channel at outfall P2. Contractor will issue a prefabricated culvert for outfall P5 to SPCDD for installation at P5. This scope is shown in Exhibit A of this Change Order.

 

2. The cost breakdowns for the scopes of work noted above in this Change Order are detailed in Exhibit B.

 

3. Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit C of this Change Order.

 

 

Adjustment to Contract Price

  

The original Contract Price was

   $ 7,080,830,000   

Net change by previously authorized Change Orders (0001-00025)

   $ 577,352,514   

The Contract Price prior to this Change Order was

   $ 7,658,182,514   

The Aggregate Equipment Price will be changed by this Change Order in the amount of

   $ ***   

The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of

   $ ***   

The new Contract Price including this Change Order will be

   $ 7,658,027,378   

 

 

Adjustment to Aggregate Equipment Price

  

The original Aggregate Equipment Price was

   $ ***   

Net change by previously authorized Change Orders (0001-00025)

   $ ***   

The Aggregate Equipment Price prior to this Change Order was

   $ ***   

The Aggregate Equipment Price will be changed by this Change Order in the amount of

   $  ***   
The new Aggregate Equipment Price including this Change Order will be    $ ***   

 

 

Adjustment to Aggregate Labor and Skills Price   

The original Aggregate Labor and Skills Price was

   $  ***   

Net change by previously authorized Change Orders (0001-00025)

   $  ***   

The Aggregate Labor and Skills Price prior to this Change Order was

   $  ***   

The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of

   $  ***   

The new Aggregate Labor and Skills Price including this Change Order will be

   $  ***   


 

Adjustment to Aggregate Provisional Sum   

The original Aggregate Provisional Sum was

   $ 950,561,351   

Net change by previously authorized Change Orders (0001-00025)

   $ (745,966,926

The Aggregate Provisional Sum prior to this Change Order was

   $ 204,594,425   

The Aggregate Provisional Sum will be changed by this Change Order in the amount of

   $ 0   

The new Aggregate Provisional Sum including this Change Order will be

   $ 204,594,425   

Adjustment to dates in Project Schedule

The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A

Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)

Adjustment to Payment Schedule: Yes. See Exhibit C of this Change Order.

Adjustment to Minimum Acceptance Criteria: N/A

Adjustment to Performance Guarantees: N/A

Adjustment to Design Basis: N/A

Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A

Select either A or B:

[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/WK Contractor /s/ EL Owner

[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner

Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.

 

/s/ Ed Lehotsky

  

/s/ Walker Kimball

Owner    Contractor

Ed Lehotsky

  

/s/ Walker Kimball

Name    Name

Senior VP LNG E+C

  

Senior Project Manager, SVP

Title    Title

October 3, 2016

  

August 31, 2016

Date of Signing    Date of Signing


*** indicates material has been omitted pursuant to a Confidential Treatment Request filed with the Securities and Exchange Commission. A complete copy of this agreement has been filed separately with the Securities and Exchange Commission.

CHANGE ORDER FORM

Anti-Dumping Duties

 

PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility

 

OWNER: Corpus Christi Liquefaction, LLC

 

CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.

 

DATE OF AGREEMENT: December 6, 2013

  

CHANGE ORDER NUMBER: CO-00028

 

DATE OF CHANGE ORDER: September 26, 2016

 

 

The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)

 

1. Per Article 6.1.B of the Agreement, Parties agree Contractor will be compensated for the costs of complying with new regulations by the U.S Department of Commerce and the U.S. International Trade Commission which impose duties on welded line pipe purchased in Turkey or Korea.

 

2. The cost breakdowns for the scopes of work noted above in this Change Order are detailed in Exhibit A.

 

3. Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit B of this Change Order.

 

 

Adjustment to Contract Price

  

The original Contract Price was

   $ 7,080,830,000   

Net change by previously authorized Change Orders (0001-00027)

   $ 580,375,680   

The Contract Price prior to this Change Order was

   $ 7,661,205,680   

The Aggregate Equipment Price will be changed by this Change Order in the amount of

   $ ***   

The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of

   $ ***   

The new Contract Price including this Change Order will be

   $ 7,661,371,904   

 

 

Adjustment to Aggregate Equipment Price

  

The original Aggregate Equipment Price was

   $  ***   

Net change by previously authorized Change Orders (0001-00027)

   $  ***   

The Aggregate Equipment Price prior to this Change Order was

   $  ***   

The Aggregate Equipment Price will be changed by this Change Order in the amount of

   $  ***   

The new Aggregate Equipment Price including this Change Order will be

   $  ***   

 

 

Adjustment to Aggregate Labor and Skills Price

  

The original Aggregate Labor and Skills Price was

     $ ***   

Net change by previously authorized Change Orders (0001-00027)

     $ ***   

The Aggregate Labor and Skills Price prior to this Change Order was

     $ ***   

The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of

     $ ***   

The new Aggregate Labor and Skills Price including this Change Order will be

     $ ***   


 

Adjustment to Aggregate Provisional Sum

  

The original Aggregate Provisional Sum was

   $ 950,561,351   

Net change by previously authorized Change Orders (0001-00027)

   $ (745,966,926

The Aggregate Provisional Sum prior to this Change Order was

   $ 204,594,425   

The Aggregate Provisional Sum will be changed by this Change Order in the amount of

   $ 0   

The new Aggregate Provisional Sum including this Change Order will be

   $ 204,594,425   

Adjustment to dates in Project Schedule

The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A

Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary) N/A

Adjustment to Payment Schedule: Yes. See Exhibit B of this Change Order.

Adjustment to Minimum Acceptance Criteria: N/A

Adjustment to Performance Guarantees: N/A

Adjustment to Design Basis: N/A

Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A

Select either A or B:

[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/WK Contractor /s/EL Owner

[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner

Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.

 

/s/ Ed Lehotsky

  

/s/ Walker Kimball

Owner    Contractor

Ed Lehotsky

  

Walker Kimball

Name    Name

Senior VP LNG E+C

  

Senior Project Manager, SVP

Title    Title

November 2, 2016

  

October 3, 2016

Date of Signing    Date of Signing


*** indicates material has been omitted pursuant to a Confidential Treatment Request filed with the Securities and Exchange Commission. A complete copy of this agreement has been filed separately with the Securities and Exchange Commission.

CHANGE ORDER FORM

Additional Flare System Evaluation

 

PROJECT NAME: Corpus Christi Stage 1 Liquefaction Facility

 

OWNER: Corpus Christi Liquefaction, LLC

 

CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc.

 

DATE OF AGREEMENT: December 6, 2013

  

CHANGE ORDER NUMBER: CO-00029

 

DATE OF CHANGE ORDER: September 26, 2016

 

 

The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)

 

1. In Change Order CO-00020, executed on June 15, 2016, the Parties agreed Contractor would conduct a study to identify a short-term solution (based on nitrogen injection) and a long-term solution (based on either high or low pressure air injection) to mitigate smoke production in the flares. In order to continue the evaluation, per Article 6.1.B of the Agreement, Parties agree Contractor will be compensated for additional costs incurred to continue its study and evaluate the solutions.

 

2. The cost breakdowns for the scopes of work noted above in this Change Order are detailed in Exhibit A.

 

3. Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the Milestone(s) listed in Exhibit B of this Change Order.

 

 

Adjustment to Contract Price

  

The original Contract Price was

   $ 7,080,830,000   

Net change by previously authorized Change Orders (0001-00028)

   $ 580,541,904   

The Contract Price prior to this Change Order was

   $ 7,661,371,904   

The Aggregate Equipment Price will be changed by this Change Order in the amount of

   $ ***   

The Aggregate Labor and Skills Price will be changed by this Change

  

Order in the amount of

   $ ***   

The new Contract Price including this Change Order will be

   $ 7,662,153,372   

 

 

Adjustment to Aggregate Equipment Price

  

The original Aggregate Equipment Price was

   $  ***   

Net change by previously authorized Change Orders (0001-00028)

   $ ***   

The Aggregate Equipment Price prior to this Change Order was

   $ ***   

The Aggregate Equipment Price will be changed by this Change Order in the amount of

   $ ***   
The new Aggregate Equipment Price including this Change Order will be    $ ***   

 

 

Adjustment to Aggregate Labor and Skills Price

  

The original Aggregate Labor and Skills Price was

   $  ***   

Net change by previously authorized Change Orders (0001-00028)

   $ ***   

The Aggregate Labor and Skills Price prior to this Change Order was

   $ ***   

The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of

   $ ***   

The new Aggregate Labor and Skills Price including this Change Order will be

   $ ***   


 

Adjustment to Aggregate Provisional Sum

  

The original Aggregate Provisional Sum was

   $ 950,561,351   

Net change by previously authorized Change Orders (0001-00028)

   $ (745,966,926

The Aggregate Provisional Sum prior to this Change Order was

   $ 204,594,425   

The Aggregate Provisional Sum will be changed by this Change Order in the amount of

   $ 0   

The new Aggregate Provisional Sum including this Change Order will be

   $ 204,594,425   

Adjustment to dates in Project Schedule

The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A

Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary) N/A

Adjustment to Payment Schedule: Yes. See Exhibit B of this Change Order.

Adjustment to Minimum Acceptance Criteria: N/A

Adjustment to Performance Guarantees: N/A

Adjustment to Design Basis: N/A

Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A

Select either A or B:

[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/WK Contractor /s/EL Owner

[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner

Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.

 

/s/ Ed Lehotsky

  

/s/ Walker Kimball

Owner    Contractor

Ed Lehotsky

  

Walker Kimball

Name    Name

Senior VP LNG E+C

  

Senior Project Manager, SVP

Title    Title

November 2, 2016

  

October 3, 2016

Date of Signing    Date of Signing