SCHEDULE D-1 CHANGE ORDER
Exhibit 10.30
SCHEDULE D-1
CHANGE ORDER
PROJECT NAME: Sabine Pass LNG Receiving, Storage and Regasification Terminal
OWNER: Sabine Pass LNG, L.P.
CONTRACTOR: Bechtel Corporation
DATE OF AGREEMENT: December 18, 2004 | CHANGE ORDER NUMBER: SP/BE-059
DATE OF CHANGE ORDER: October 17, 2008
Ready for Performance Testing |
The Agreement between the Parties listed above is changed as follows:
The defined term for Ready for Performance Testing set forth in Article 1.1 of the Agreement is hereby deleted in its entirety and replaced with the following definition:
Ready for Performance Testing means that all of the following have occurred with respect to the Facility: (i) Cool Down has been completed for System 1, System 2, and System 3; (ii) all vaporizers have been operated individually; (iii) Contractor has completed all procurement, fabrication, assembly, erection, installation and pre-commissioning checks and tests of the Facility to ensure that the entire Work and each component thereof was sufficiently fabricated, assembled, erected and installed so as to be capable of being operated safely within the requirements contained in this Agreement; and (iv) all portions of the Facility have attained the state of completion necessary for commencement of the Sendout Rate Performance Test.
Adjustment to Contract Price | |||
The original Contract Price was | $ | 646,936,000 | |
Net change by previously authorized Change Orders (#SP/BE-002 to 028, 031, 033 thru 035; 037 thru 058) | $ | 182,442,446 | |
The Contract Price prior to this Change Order was | $ | 829,378,446 | |
The Contract Price will be increased by this Change Order in the amount of | $ | 0.00 | |
The new Contract Price including this Change Order will be | $ | 829,378,446 |
Adjustment to dates in Project Schedule
The following dates are modified:
The Target Bonus Date is July 18, 2008.
The Guaranteed Substantial Completion Date will be unchanged (December 20, 2008).
The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is 1,355 days following NTP.
Adjustment to other Changed Criteria: No Change
Adjustment to Payment Schedule: No Change
Adjustment to Minimum Acceptance Criteria: As modified by this Change Order
Adjustment to Performance Guarantees: As modified by this Change Order
Adjustment to Design Basis: No Change.
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: As modified by this Change Order.
Change Order #59 Ready for Performance Testing | 1 of 2 |
This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change as described in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change.
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties duly authorized representatives.
/s/ Charif Souki | /s/ Patrick McCormack | |||
* Charif Souki | Contractor | |||
Chairman | Patrick McCormack | |||
Name | ||||
Project Director | ||||
Title | ||||
November 11, 2008 | 31 Oct 08 | |||
Date of Signing | Date of Signing |
/s/ Keith Teague |
* Keith Teague |
Senior Vice President |
10 Nov 2008 |
Date of Signing |
/s/ Ed Lehotsky |
* Ed Lehotsky |
Owner Representative |
10 Nov 2008 |
Date of Signing |
* | Required Owner signature Mr. Teague may sign on behalf of Mr. Souki during Mr. Soukis absence. |
Change Order #59 Ready for Performance Testing | 2 of 2 |