Change orders to the Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 4 Liquefaction Facility, dated November 7, 2018, by and between SPL and Bechtel Oil Gas and Chemicals, Inc.: (i) the Change Order CO-00070 80-Acres Bridge, dated October 28, 2022, (ii) the Change Order CO-00071 Mooring System Low-Tension Common Alarm, dated October 31, 2022, (iii) the Change Order CO-00072 FERC Hydrocarbon Permit Conditions, dated October 31, 2022
Contract Categories:
Business Finance
- Facility Agreements
EX-10.92 5 exhibit1092cei2022form10k.htm EX-10.92 Document
Exhibit 10.92
CHANGE ORDER
80-ACRES BRIDGE
PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00070 DATE OF CHANGE ORDER: 28-Oct-2022 |
The Agreement between the Parties listed above is changed as follows:
1. In accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), the Parties agree this Change Order includes Contractor’s costs to provide the Engineering, Procurement, and Construction services to install a permanent beam bridge (“80 Acres Bridge”) between the 80 Acres real estate and Lighthouse Road. This Change Order comprises:
a.A concrete slab beam design with 12ea concrete beams; and
b.Includes for the demolition and removal of the existing north and south bridges.
2. For context this Change Order, therefore, addresses Work that Contractor commenced and subsequently discontinued under Change Orders CO-00047 and CO-00054, executed on 18-Jun-2021 and 01-Dec-2021 respectively.
3. The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order.
4. Schedule C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order.
Adjustment to Contract Price Applicable to Subproject 6(a)
1. The original Contract Price Applicable to Subproject 6(a) was | $ | 2,016,892,573 | |||
2. Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#01-08, 10-13, 15, 17-18, 21-22, 24, 28-29, 31-32, 34-35, 38, 41-42, 45-49, 51, 53-58, 61) | $ | 697,987 | |||
3. The Contract Price Applicable to Subproject 6(a) prior to this Change Order was | $ | 2,017,590,560 | |||
4. The Contract Price Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of | $ | — | |||
5. The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of | $ | — | |||
6. The Contract Price Applicable to Subproject 6(a) including this Change Order will be | $ | 2,017,590,560 |
Adjustment to Contract Price Applicable to Subproject 6(b)
7. The original Contract Price Applicable to Subproject 6(b) (in CO-00009) was | $ | 457,696,000 | |||
8. Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#14, 16, 19-20, 23, 25-27, 30-31, 33, 36-37, 39-40, 43-44, 50, 52, 59-60, 62-69) | $ | 7,578,450 | |||
9. The Contract Price Applicable to Subproject 6(b) prior to this Change Order was | $ | 465,274,450 | |||
10. The Contract Price Applicable to Subproject 6(b) will be changed by this Change Order | $ | 1,584,805 | |||
11. The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order | $ | — | |||
12. The Contract Price Applicable to Subproject 6(b) including this Change Order will be | $ | 466,859,255 |
Adjustment to Contract Price
13. The original Contract Price for Subproject 6(a) and Subproject 6(b) was (add lines 1 and 7) | $ | 2,474,588,573 | |||
14. The Contract Price prior to this Change Order was (add lines 3 and 9) | $ | 2,482,865,010 |
15. The Contract Price will be increased by this Change Order in the amount of (add lines 4, 5, 10 and 11) | $ | 1,584,805 | |||
16. The new Contract Price including this Change Order will be (add lines 14 and 15) | $ | 2,484,449,815 |
Adjustment to dates in Project Schedule for Subproject 6(a)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(a): N/A
Adjustment to Payment Schedule for Subproject 6(a): N/A
Adjustment to Minimum Acceptance Criteria for Subproject 6(a): N/A
Adjustment to Performance Guarantees for Subproject 6(a): N/A
Adjustment to Design Basis for Subproject 6(a): N/A
Other adjustments to liability or obligations of Contractor or Owner under the Agreement for Subproject 6(a): N/A
Adjustment to dates in Project Schedule for Subproject 6(b)
The following dates are modified: N/A – This Work is performed post-Substantial Completion
Adjustment to other Changed Criteria for Subproject 6(b): N/A – This Work is performed post-Substantial Completion
Adjustment to Payment Schedule for Subproject 6(b): Yes; see Exhibit B
Adjustment to Design Basis for Subproject 6(b): N/A - This Work is performed post-Substantial Completion
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A - This Work is performed post-Substantial Completion
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ SS Contractor /s/ DC Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ David Craft | /s/ Steve Smith | |||||||
Owner | Contractor | |||||||
David Craft | Steve Smith | |||||||
Name | Name | |||||||
SVP E&C | Senior Project Manager & Principal Vice President | |||||||
Title | Title | |||||||
November 18, 2022 | ||||||||
Date of Signing | Date of Signing |
CHANGE ORDER
MOORING SYSTEM LOW-TENSION COMMON ALARM
PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00071 DATE OF CHANGE ORDER: 31-Oct-2022 |
The Agreement between the Parties listed above is changed as follows:
1.In accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), the Parties agree this Change Order includes Contractor’s costs to provide the Procurement and Construction services to add a Low-Tension Common Alarm to the East, West and Third Berth jetties’ mooring systems.
2.The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order.
3.Schedule C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order.
Adjustment to Contract Price Applicable to Subproject 6(a)
1. The original Contract Price Applicable to Subproject 6(a) was | $ | 2,016,892,573 | |||
2. Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#01-08, 10-13, 15, 17-18, 21-22, 24, 28-29, 31-32, 34-35, 38, 41-42, 45-49, 51, 53-58, 61, 68) | $ | 697,987 | |||
3. The Contract Price Applicable to Subproject 6(a) prior to this Change Order was | $ | 2,017,590,560 | |||
4. The Contract Price Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of | $ | — | |||
5. The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of | $ | — | |||
6. The Contract Price Applicable to Subproject 6(a) including this Change Order will be | $ | 2,017,590,560 |
Adjustment to Contract Price Applicable to Subproject 6(b)
7. The original Contract Price Applicable to Subproject 6(b) (in CO-00009) was | $ | 457,696,000 | |||
8. Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#14, 16, 19-20, 23, 25-27, 30-31, 33, 36-37, 39-40, 43-44, 50, 52, 59-60, 62-70) | $ | 9,163,255 | |||
9. The Contract Price Applicable to Subproject 6(b) prior to this Change Order was | $ | 466,859,255 | |||
10. The Contract Price Applicable to Subproject 6(b) will be unchanged by this Change Order | $ | 71,174 | |||
11. The Provisional Sum Applicable to Subproject 6(b) will be changed by this Change Order | $ | — | |||
12. The Contract Price Applicable to Subproject 6(b) including this Change Order will be | $ | 466,930,429 |
Adjustment to Contract Price
13. The original Contract Price for Subproject 6(a) and Subproject 6(b) was (add lines 1 and 7) | $ | 2,474,588,573 | |||
14. The Contract Price prior to this Change Order was (add lines 3 and 9) | $ | 2,484,449,815 | |||
15. The Contract Price will be increased by this Change Order in the amount of (add lines 4, 5, 10 and 11) | $ | 71,174 | |||
16. The new Contract Price including this Change Order will be (add lines 14 and 15) | $ | 2,484,520,989 |
Adjustment to dates in Project Schedule for Subproject 6(a)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(a): N/A
Adjustment to Payment Schedule for Subproject 6(a): N/A
Adjustment to Minimum Acceptance Criteria for Subproject 6(a): N/A
Adjustment to Performance Guarantees for Subproject 6(a): N/A
Adjustment to Design Basis for Subproject 6(a): N/A
Other adjustments to liability or obligations of Contractor or Owner under the Agreement for Subproject 6(a): N/A
Adjustment to dates in Project Schedule for Subproject 6(b)
The following dates are modified: N/A – This Work is performed post-Substantial Completion
Adjustment to other Changed Criteria for Subproject 6(b): N/A – This Work is performed post-Substantial Completion
Adjustment to Payment Schedule for Subproject 6(b): Yes; see Exhibit B
Adjustment to Design Basis for Subproject 6(b): N/A – This Work is performed post-Substantial Completion
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A – This Work is performed post-Substantial Completion
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ SS Contractor /s/ DC Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ David Craft | /s/ Steve Smith | |||||||
Owner | Contractor | |||||||
David Craft | Steve Smith | |||||||
Name | Name | |||||||
SVP E&C | Senior Project Manager & Principal Vice President | |||||||
Title | Title | |||||||
November 18, 2022 | ||||||||
Date of Signing | Date of Signing |
CHANGE ORDER
FERC HYDROCARBON PERMIT CONDITIONS
PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00072 DATE OF CHANGE ORDER: 31-Oct-2022 |
The Agreement between the Parties listed above is changed as follows:
1. In accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), and as per the requirements stated in Owner correspondence SPL4-BE-C22-023 dated 02-Sep-2022, the Parties agree this Change Order includes Contractor’s costs to provide the Engineering, Procurement, and Construction services for:
a.A passive system designed to withstand a 20-minute fire exposure per UL 1709 for instrumented valves in Subproject 6(b) which activate emergency systems under Condition 79 and associated conditions;
b.Flame detection covering a minimum of 90% of all areas by two or more detectors that contain flammable or combustible fluids, including the entire length of the marine transfer piping and valve platform, under Condition 64 and associated conditions;
c.Replacement of sodium bicarbonate extinguishers with potassium bicarbonate extinguishers in areas where LNG is handled under Condition 73 and associated conditions; and
d.Firewater hydrants or monitors for the entire length of the marine transfer piping, under Condition 80 and associated conditions.
2. The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order.
3. Schedule C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order.
Adjustment to Contract Price Applicable to Subproject 6(a) | |||||
1. The original Contract Price Applicable to Subproject 6(a) was | $ | 2,016,892,573 | |||
2. Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#01-08, 10-13, 15, 17-18, 21-22, 24, 28-29, 31-32, 34-35, 38, 41-42, 45-49, 51, 53-58, 61, 68) | $ | 697,987 | |||
3. The Contract Price Applicable to Subproject 6(a) prior to this Change Order was | $ | 2,017,590,560 | |||
4. The Contract Price Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of | $ | — | |||
5. The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of | $ | — | |||
6. The Contract Price Applicable to Subproject 6(a) including this Change Order will be | $ | 2,017,590,560 | |||
Adjustment to Contract Price Applicable to Subproject 6(b) | |||||
7. The original Contract Price Applicable to Subproject 6(b) (in CO-00009) was | $ | 457,696,000 | |||
8. Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#14, 16, 19-20, 23, 25-27, 30-31, 33, 36-37, 39-40, 43-44, 50, 52, 59-60, 62-71) | $ | 9,234,429 | |||
9. The Contract Price Applicable to Subproject 6(b) prior to this Change Order was | $ | 466,930,429 | |||
10. The Contract Price Applicable to Subproject 6(b) will be changed by this Change Order | $ | 1,308,101 | |||
11. The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order | $ | — | |||
12. The Contract Price Applicable to Subproject 6(b) including this Change Order will be | $ | 468,238,530 | |||
Adjustment to Contract Price | |||||
13. The original Contract Price for Subproject 6(a) and Subproject 6(b) was (add lines 1 and 7) | $ | 2,474,588,573 | |||
14. The Contract Price prior to this Change Order was (add lines 3 and 9) | $ | 2,484,520,989 |
15. The Contract Price will be increased by this Change Order in the amount of (add lines 4, 5, 10 and 11) | $ | 1,308,101 | |||
16. The new Contract Price including this Change Order will be (add lines 14 and 15) | $ | 2,485,829,090 |
Adjustment to dates in Project Schedule for Subproject 6(a)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(a): N/A
Adjustment to Payment Schedule for Subproject 6(a): N/A
Adjustment to Minimum Acceptance Criteria for Subproject 6(a): N/A
Adjustment to Performance Guarantees for Subproject 6(a): N/A
Adjustment to Design Basis for Subproject 6(a): N/A
Other adjustments to liability or obligations of Contractor or Owner under the Agreement for Subproject 6(a): N/A
Adjustment to dates in Project Schedule for Subproject 6(b)
The following dates are modified: N/A - This Work is performed post-Substantial Completion
Adjustment to other Changed Criteria for Subproject 6(b): N/A - This Work is performed post-Substantial Completion
Adjustment to Payment Schedule for Subproject 6(b): Yes; see Exhibit B
Adjustment to Design Basis for Subproject 6(b): N/A - This Work is performed post-Substantial Completion
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A - This Work is performed post-Substantial Completion
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: _SS_ Contractor ____ Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ David Craft | /s/ Steve Smith | |||||||
Owner | Contractor | |||||||
David Craft | Steve Smith | |||||||
Name | Name | |||||||
SVP E&C | Senior Project Manager & Principal Vice President | |||||||
Title | Title | |||||||
November 18, 2022 | ||||||||
Date of Signing | Date of Signing |
CHANGE ORDER
BN#2 BEACON PILE RELOCATION
PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00073 DATE OF CHANGE ORDER: 31-Oct-2022 |
The Agreement between the Parties listed above is changed as follows:
1. In accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), the Parties agree this Change Order includes Contractor’s costs to relocate the Third Berth’s Beacon Pile BN#2 to an adjacent location in accordance with direction from the Sabine Bank Pilots Association. Refer to Attachment 1 of this Change Order.
2. The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order.
3. Schedule C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order.
Adjustment to Contract Price Applicable to Subproject 6(a) | |||||
1. The original Contract Price Applicable to Subproject 6(a) was | $ | 2,016,892,573 | |||
2. Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#01-08, 10-13, 15, 17-18, 21-22, 24, 28-29, 31-32, 34-35, 38, 41-42, 45-49, 51, 53-58, 61, 68) | $ | 697,987 | |||
3. The Contract Price Applicable to Subproject 6(a) prior to this Change Order was | $ | 2,017,590,560 | |||
4. The Contract Price Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of | $ | — | |||
5. The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of | $ | — | |||
6. The Contract Price Applicable to Subproject 6(a) including this Change Order will be | $ | 2,017,590,560 | |||
Adjustment to Contract Price Applicable to Subproject 6(b) | |||||
7. The original Contract Price Applicable to Subproject 6(b) (in CO-00009) was | $ | 457,696,000 | |||
8. Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#14, 16, 19-20, 23, 25-27, 30-31, 33, 36-37, 39-40, 43-44, 50, 52, 59-60, 62-72) | $ | 10,542,530 | |||
9. The Contract Price Applicable to Subproject 6(b) prior to this Change Order was | $ | 468,238,530 | |||
10. The Contract Price Applicable to Subproject 6(b) will be changed by this Change Order | $ | 53,097 | |||
11. The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order | $ | — | |||
12. The Contract Price Applicable to Subproject 6(b) including this Change Order will be | $ | 468,291,627 | |||
Adjustment to Contract Price | |||||
13. The original Contract Price for Subproject 6(a) and Subproject 6(b) was (add lines 1 and 7) | $ | 2,474,588,573 | |||
14. The Contract Price prior to this Change Order was (add lines 3 and 9) | $ | 2,485,829,090 | |||
15. The Contract Price will be increased by this Change Order in the amount of (add lines 4, 5, 10 and 11) | $ | 53,097 | |||
16. The new Contract Price including this Change Order will be (add lines 14 and 15) | $ | 2,485,882,187 |
Adjustment to dates in Project Schedule for Subproject 6(a)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(a): N/A
Adjustment to Payment Schedule for Subproject 6(a): N/A
Adjustment to Minimum Acceptance Criteria for Subproject 6(a): N/A
Adjustment to Performance Guarantees for Subproject 6(a): N/A
Adjustment to Design Basis for Subproject 6(a): N/A
Other adjustments to liability or obligations of Contractor or Owner under the Agreement for Subproject 6(a): N/A
Adjustment to dates in Project Schedule for Subproject 6(b)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(b): N/A
Adjustment to Payment Schedule for Subproject 6(b): Yes; see Exhibit B
Adjustment to Design Basis for Subproject 6(b): N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ SS Contractor /s/ DC Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ David Craft | /s/ Steve Smith | |||||||
Owner | Contractor | |||||||
David Craft | Steve Smith | |||||||
Name | Name | |||||||
SVP E&C | Senior Project Manager & Principal Vice President | |||||||
Title | Title | |||||||
November 18, 2022 | ||||||||
Date of Signing | Date of Signing |
CHANGE ORDER
FERC CONDITION 56: ISA 84 GAS DETECTION
PROJECT NAME: Sabine Pass LNG Stage 4 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: November 7, 2018 | CHANGE ORDER NUMBER: CO-00074 DATE OF CHANGE ORDER: 31-Oct-2022 |
The Agreement between the Parties listed above is changed as follows:
1. In accordance with Section 6.1 of the Agreement (Change Orders Requested by Owner), the Parties agree this Change Order includes Contractor’s costs to provide the Engineering, Procurement, and Construction services to comply with FERC Condition 56 referred in Aconex transmittal SPL4-E-EM-TRM-00217 (“Societal Risk from LNG Spills on Water”), that is, installing 11ea gas detectors to justify the 10-minute release duration assumed in the Quantitative Risk Assessment that was performed to address Condition 56.
2. The detailed cost breakdown for this Change Order is detailed in Exhibit A of this Change Order.
3.Schedule C-3 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order.
Adjustment to Contract Price Applicable to Subproject 6(a)
1. The original Contract Price Applicable to Subproject 6(a) was | $ | 2,016,892,573 | |||
2. Net change for Contract Price Applicable to Subproject 6(a) by previously authorized Change Orders (#01-08, 10-13, 15, 17-18, 21-22, 24, 28-29, 31-32, 34-35, 38, 41-42, 45-49, 51, 53-58, 61, 68) | $ | 697,987 | |||
3. The Contract Price Applicable to Subproject 6(a) prior to this Change Order was | $ | 2,017,590,560 | |||
4. The Contract Price Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of | $ | — | |||
5. The Provisional Sum Applicable to Subproject 6(a) will be unchanged by this Change Order in the amount of | $ | — | |||
6. The Contract Price Applicable to Subproject 6(a) including this Change Order will be | $ | 2,017,590,560 |
Adjustment to Contract Price Applicable to Subproject 6(b)
7. The original Contract Price Applicable to Subproject 6(b) (in CO-00009) was | $ | 457,696,000 | |||
8. Net change for Contract Price Applicable to Subproject 6(b) by previously authorized Change Orders (#14, 16, 19-20, 23, 25-27, 30-31, 33, 36-37, 39-40, 43-44, 50, 52, 59-60, 62-73) | $ | 10,595,627 | |||
9. The Contract Price Applicable to Subproject 6(b) prior to this Change Order was | $ | 468,291,627 | |||
10. The Contract Price Applicable to Subproject 6(b) will be changed by this Change Order | $ | 443,977 | |||
11. The Provisional Sum Applicable to Subproject 6(b) will be unchanged by this Change Order | $ | — | |||
12. The Contract Price Applicable to Subproject 6(b) including this Change Order will be | $ | 468,735,604 |
Adjustment to Contract Price
13. The original Contract Price for Subproject 6(a) and Subproject 6(b) was (add lines 1 and 7) | $ | 2,474,588,573 | |||
14. The Contract Price prior to this Change Order was (add lines 3 and 9) | $ | 2,485,882,187 | |||
15. The Contract Price will be increased by this Change Order in the amount of (add lines 4, 5, 10 and 11) | $ | 443,977 | |||
16. The new Contract Price including this Change Order will be (add lines 14 and 15) | $ | 2,486,326,164 |
Adjustment to dates in Project Schedule for Subproject 6(a)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(a): N/A
Adjustment to Payment Schedule for Subproject 6(a): N/A
Adjustment to Minimum Acceptance Criteria for Subproject 6(a): N/A
Adjustment to Performance Guarantees for Subproject 6(a): N/A
Adjustment to Design Basis for Subproject 6(a): N/A
Other adjustments to liability or obligations of Contractor or Owner under the Agreement for Subproject 6(a): N/A
Adjustment to dates in Project Schedule for Subproject 6(b)
The following dates are modified: N/A
Adjustment to other Changed Criteria for Subproject 6(b): N/A
Adjustment to Payment Schedule for Subproject 6(b): Yes; see Exhibit B
Adjustment to Design Basis for Subproject 6(b): N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ SS Contractor /s/ DC Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ David Craft | /s/ Steve Smith | |||||||
Owner | Contractor | |||||||
David Craft | Steve Smith | |||||||
Name | Name | |||||||
SVP E&C | Senior Project Manager & Principal Vice President | |||||||
Title | Title | |||||||
November 18, 2022 | ||||||||
Date of Signing | Date of Signing |