Quality Specifications
EX-10.26 17 c64870a5exv10w26.htm EX-10.26 exv10w26
Exhibit 10.26
Tennessee Valley Authority
Coal Acquisition & Supply
1101 Market Street, MR 2A
Chattanooga, Tennessee ###-###-####
CONTRACT SUPPLEMENT
Coal Acquisition & Supply
1101 Market Street, MR 2A
Chattanooga, Tennessee ###-###-####
CONTRACT SUPPLEMENT
TO: | Armstrong Coal Company, Inc. | Supplement No. | 2 | |||||
7701 Forsyth Boulevard - 10th Floor | Date | October 9, 2009 | ||||||
St. Louis, Missouri 63105 | Group-Contract No. | 635-40685 | ||||||
Plant | Various | |||||||
Name of Mine | Various |
Attention: Mr. Martin Wilson
This confirms the October 1, 2009, agreement reached between both parties relative to freeze proofing deliveries under the subject contracts.
As agreed, the freeze proofing products that will be applied to TVAs shipments will be FreeFlowFC-100 for body feed application and FreeFlowSR-300 for side car release application. Both products are manufactured by AKJ Industries, and will be applied to coal loaded for TVAs fossil plants as follows:
1. | Unless TVA notifies contractor otherwise, anytime the temperature at contractors loading facility is below 27 degrees Fahrenheit during the loading process, contractor will apply approximately 2 pints of FreeFlowFC-100 to each ton of coal being loaded into railcars at Contractors facilities. This amount may be adjusted by mutual agreement of the parties to reduce the risk of frozen coal being delivered to TVAs plants. The exception to this rule applies in the event a cooling period is moving into the area in 48 hours, dropping the temperature for an extended period of time. | |
2. | The cost to TVA for applying FreeFlowFC-100 will be $2.00 per gallon or $.50 per 2 pint application. | |
3. | The cost to TVA for applying the side care release application, FreeFlowSr-300, upon TVAs request, will be $2.80 per gallon or $.35 per 1 pint application. | |
4. | Contractor will invoice separately for the cost of applying FreeFlowFC-100 and FreeFlowSR-300. Each invoice and all correspondence relating to the application of the freeze conditioning substance(s) should clearly reflect the Contract number, Traffic Control Number, and the cost of such treatment. Invoices for freeze conditioning should be sent to the attention of Connie Gazaway at Tennessee Valley Authority, 1101 Market Street, MR 2A, Chattanooga, Tennessee ###-###-####. | |
Please complete the acceptance below and return the copy of this contract supplement to this office. You should retain the original for your file. |
In the event Contractor fails to execute this Supplement in the acceptance space provided below or fails to return such executed Supplement to TVA, shipment of coal to TVA following the date of Contractors receipt of this Supplement shall constitute an acceptance by Contractor of all the terms and conditions of this Supplement, unless within five (5) business days of the date of receipt of this Supplement, Contractor notifies TVA, both orally and in writing that this Supplement is not accepted. |
Accepted | Armstrong Coal Co. | TENNESSEE VALLEY AUTHORITY | ||||
Company | ||||||
By | /s/ Martin D. Wilson | /s/ Connie S. Gazaway | ||||
Fuel Transportation Specialist | ||||||
President | /s/ | |||||
Title | Contract Support Specialist | |||||
11/5/09 | /s/ | |||||
Date | Manager of Coal Supply |