Exhibit 10.44
Confidential Materials omitted and filed separately with the
Securities and Exchange Commission. Asterisks denote omissions.
The Purchase Contract No. FDCG08050
for the Electrical System of SL 3000 Wind Turbine
This Purchase Contract is signed between:
Sinovel Wind Co., Ltd (hereinafter referred to as Buyer)
Buyers Agent: China National Machinery & Equipment Import & Export Corporation (hereinafter referred to as Buyers agent)
And
Windtec Systemtechnik Handels GmbH in Austria (hereinafter referred to as Seller) in a friendly way.
The contract equipment is used for the purchasing contract of the electrics for SL 3000 wind turbine which is signed between Buyer and Seller.
Buyer and Seller agreed as follows:
1. | Definition |
In construing this contract, the following words and expressions shall have the meanings hereby assigned to them unless otherwise specified in the contract.
1.1 | Contact means this contract, including Article 1 to Article 20. |
1.2 | Contract price means the price payable to Seller under the contract for the full and proper performance of its contractual obligations, which is not influenced by the price fluctuations. |
1.3 | Contract currency means the currency used in the payment under the contract, which is Euro. |
1.4 | Buyers Bank means Bank of China designated by Buyer for the other banks designated by Seller. |
1.5 | Sellers Bank means Bank Austria Creditanstalt AG. |
1.6 | Effective date of the contract means the date when the contract enters into force upon fulfillment of the conditions stated in Article 20. |
1.7 | Contract equipment means the 50 Hz electrics of SL 3000 wind turbine. |
1
2. | Scope of Supply: |
Each set comprises of:
Pos. | Name | No. | Units | Total Price | ||||
1 | Nacelle Cabinet (incl. Converter) plus Power Supply Cabinet (located in TB) | +CC300/+CC310 | 1 | EUR [**] | ||||
+NC300/+NC310 | EUR [**] | |||||||
+PSC100 | EUR [**] | |||||||
+CRO300 | EUR [**] | |||||||
2 | IPS (Internal Power Supply) | +IPS100 | 1 | EUR [**] | ||||
3 | Slip Ring inc,. Overvoltage Protection | +SR300/+OVP400 | 1 | EUR [**] | ||||
4 | Hub Cabinets inc,. Power Caps Cabinets | +HC400/+HC410 | 3 | EUR [**] | ||||
+HC420/+PC400/ | ||||||||
+PC410/+PC420 | ||||||||
5 | Servo Pitch Motor | +PM400/+PM410/ | 3 | EUR [**] | ||||
+PM420 | ||||||||
6 | Tower Base Cabinet incl. SCADA | +TBC100 | 1 | EUR [**] | ||||
7 | CMS (Condition Monitoring System)(1) | 1 | EUR [**] | |||||
- incl. CPU MX213 | ||||||||
- incl. AIC 212 Module | ||||||||
- incl. Dummy Module LM201 | ||||||||
- incl. Electrical Cabinet MKL4 machined | ||||||||
TOTAL VALUE | EUR [**] | |||||||
(1) | Sensors are beyond SELLERs scope of core components supply. The respective specification shall be defined by SELLER but purchased by BUYER separately. |
3. | Quantities: |
Total number of goods is 4 sets.
4. | Price |
The total contracting price will be [**] Euros (INCOTERNS 2000, FOB packed).
5. | Port of shipment: |
Goods shall be on shipment from main European seaport or Austria airport.
6. | Delivery Period: |
The delivery will be made in batches as per preliminary schedule below.
CW 30, 2008 [**] sets, tested
CW 35, 2008 [**] sets, tested
2
7. | Documentation |
Seller shall provide to the Buyer the certificate and test report of the converter together with the equipment.
8. | Payment Schedule |
95% by L/C at sight.
Two weeks before each shipment date, an irrevocable Letter of Credit at an amount of 95% of each shipment value shall be issued by a first class bank. The L/C shall be according to ICP600. If L/C is delayed, the delivery time will be postponed accordingly.
5% Retention Bond:
The Retention Bond shall be paid upon the expiry of warranty period of 24 months after finished commissioning, or 30 months after the delivery, whichever is earlier within 14 days, under the precondition that the availability of the electrical control system for each WT is at least [**]% during such period. Such percentage will be the average of a respective wind park. The dependency of this 5%-payment from an availability of [**]% will only be on the condition that (i) control cabinets have been manufactured by BUYER under supervision and instruction of Seller, (ii) test and quality of electrical cabinets have been released by Seller, (iii) fault of electrical control system will be diagnosed by Seller, (iv) replacement of components will be executed by BUYER within 24 hours, and (v) Seller will have continuous and full access to the SCADA system of the respective wind turbines.
BUYER is responsible for item I-V. If any of these items is not fulfilled, the retention bond has to be paid to Seller even in case of an availability of at least [**]% has not been reached.
Seller must provide the following performance bond to Buyer:
Within 30 days after effectiveness of the contract, SELLER shall through SELLERs bank open an irrevocable performance bond in favour of BUYER, for an amount of EUR 100,000.00. Validity of the guarantee shall be by the end of February 2009.
9. | The Seller shall supply the following documents as part of L/C paperwork: |
| B/L or Air Way Bill |
| Commercial Invoice |
| Packing List |
| Certificate of Origin |
| Certificate of quarantine for Packing Wood; Declaration for Packing Wood issued by Seller marking IPPC |
| Shipping Advice |
| Quality Certificate |
The details refer to the detailed definition in L/C.
3
10. | Delivery notice |
Seller shall complete the delivery of Contract Equipment in batches and on time as required in article 6. Two (2) weeks before shipping, Buyer will be informed about the exact date of delivery.
11. | Packing and Marking |
Unless otherwise specified in the contract, the contract equipment shall be packed by Seller in a properly manner. And necessary measures shall be taken to protect the contract equipment from moisture, rain, rust, corrosion, shock and other damages according to their different characteristics so as to withstand numerous handling, loading and unloading as well as long distance sea and inland transportation.
The following documents shall be enclosed in each package of the Contract Equipment:
| Two (2) copies of detailed packing list; |
| Two (2) of quality certificate; |
| One (1) copy of technical documentation for relevant Contract Equipment. |
12. | Inspection |
Seller shall inspect the Contract Equipment and issue the quality certificates as well as inspection records. All involved expenses shall be for Sellers account. The quality certificates and inspection records including detail and result of inspection before delivery shall be submitted by Seller to Buyer.
13. | Warranty |
Seller warrants, that the Contract Equipment shall be completely new, advanced in technology and superior in quality, free from any defect in design, material and workmanship, suitable for the use and purpose and in conformity with the technical specification.
Seller warrants that the technical documentation shall be complete, clear and correct. Warranty period is 24 months after finished commissioning, or 30 months after the delivery, whichever is earlier.
Warranty means within warranty period in case of any damage or problem of any core components, that the components for replacement will be provided by Seller free of charge and Seller should ensure timely supply of spare parts. Seller shall correct any such failure either at its option, (i) by repairing any defective or damaged part or parts or the supplied products, or (ii) by making available any necessary repaired or replacement parts. Fault of electrical control system will be diagnosed by Seller and replacement of components will be executed by BUYER, each party at his own expense.
14. | Penalty for delayed delivery |
In case of delayed delivery of any shipment, starting from the second week of delay, every week of delay will be charged [**]% of the price of the delayed set as penalty, only a delay for more than 4 days is counted as one complete week Sum of the above mentioned penalty shall not exceed [**]% of the total contract price. Payment of the delayed delivery penalty shall not relieve Seller from the obligation of continuing delivery of relevant contract equipment.
4
15. | Claims |
15.1 In case the Contract Equipment supplied by Seller does not meet the specified technical performance during the Warranty Period and Seller doesnt fulfill his responsibility according to article 13, Buyer has the right to lodge claims against Seller, and Seller shall settle the claims upon the agreement of Buyer in the following way:
1) Repair or remove the defects and discrepancies of the equipment at Sellers expense. In case Seller cannot send his personnel to the Job Site, Buyer shall have the right to do the repair or removal of the defects and discrepancies and all the expensed incurred should be borne by Seller.
2) Replace the defective equipment or technical documents with new one at Sellers expenses and Seller shall guarantee the quality of the replaced equipment for a recalculated warrantee period. The replaced and/or supplemented equipment shall be delivered DDP to the Job Site.
In case Seller fails to make proposals for settling the claims according to any and/or all the ways mentioned above within 14 days after notification of the claim raised by Buyer, Buyer shall have the right to recover the claimed amount from Retention Bond (maximum up to 5% of the total contract price).
15.2 The notice of claim for the defective equipment shall be effective if it is issued not later than thirty (30) days after the expiration of the Warranty Period, but the claim must be detected within the warranty period (proved and reported by an independent expert).
15.3 In case Seller fails to accept the claim within thirty (30) days after receipt of Buyers claim, the claim shall be regarded as not acceptable by Seller.
16. | Force Majeure |
Neither party shall be held responsible for failure or delay to perform all or any party of this contract due to flood, fire, earthquake, snowstorm, drought, hailstorm, hurricane, or any other events that are beyond the control of the affected party and could not reasonably be expected at the time of conclusion of the contract or have been avoided or overcome by such party. However, the party whos performance is affected by the event of Force Majeure shall give a notice to the other party of its occurrence as soon as possible and a certificate or a document of the occurrence of the Force Majeure event issued by the relative authority or a neutral independent third party shall be sent to the other party not later than (14) days after its occurrence. If the event of Force Majeure event continues for more than (180) days, both parties shall negotiate the performance or the termination of this contract. In the case of such a termination either party shall bear its own costs, further claims for compensation in connection with the termination shall be excluded.
17. | Taxes and Duties |
17.1 All taxes in connection with and in the execution of the contract levied by the Chinese government on Buyer in accordance with the tax laws of P.R. China shall be borne by Buyer.
5
17.2 All taxed levied by the Chinese government on Seller, in connection with and in the execution of the contract, according to Chinese tax laws and the agreement between the government of the Peoples Republic of China and the Government of Sellers country for the reciprocal avoidance of double taxation and the prevention of fiscal evasion with respect to taxes on income shall be borne by Seller.
17.3 All taxes arising outside of China in connection with and in execution of the contract shall be borne by Seller.
18. | Arbitration |
All disputes arising from, or in connection with the execution of the contract, shall be settled through friendly discussion between the two parties. In case no agreement can be reached throughout, the disputes shall be submitted to Chamber of Commerce in Zurich Switzerland, for Arbitration.
Not withstanding any reference to arbitration, the two parties shall continue to perform their respective obligations under the contact unless the two parties otherwise agree.
19. | Termination |
19.1 Buyer may, without prejudice to any remedy by Seller for Sellers following breach of contract, by written notice of default sent to Seller, terminate the contract in whole or in part, if Seller fails to deliver any or all of the contract Equipment within 120 days after the delivery time specified in Article 6.
19.2 Buyer may at any time terminate the contract, by giving written notice to Seller in case Seller becomes bankrupt or otherwise insolvent, and such termination does not prejudice or affect any right of action or remedy available to Buyer. The same applies vice versa to Seller.
20. | Effectiveness of the Contract and Miscellaneous |
20.1 | The contract becomes valid on signing by the authorized representatives of the two parties of the Contract. |
20.2 | The present contract shall be valid for 3 years from the effective date of the contract, however the contract shall become null and void automatically when each party of the contract has fulfilled its rights and obligations under the contract. |
20.3 | At the expiration of the Contract, any unsettled credit and debt under the Contract shall not be affected by the expiration of the Contract. The debtor shall still effect his obligation of reimbursement to the creditor. |
20.4 | The Contract shall be made in English. |
20.5 | All amendments, supplements and alternations to the terms and conditions of the Contract shall be made in written form and signed by the authorized representatives of the two Parties. |
20.6 | Unless otherwise stipulated in the Contract, the terms and conditions of the Contract shall be interpreted in accordance with INCOTERMS (2000 Edition). |
20.7 | No assignment of any right or obligation under the Contract shall be made by either party to a third party without the previous consent of the other party. |
6
20.8 | The communication between the two parties shall be conducted in written form. The fax concerning the important matter shall be confirmed timely by the registered or express mail. |
Buyer: Sinovel Wind Co., Ltd
Address: Culture Building, No.59, Zhongguancun Street, Haidian, Beijing, China
Post code: 100872
Fx: (0086) 10-82500072
Ph: (0086) 10-62515566
Liu Zhengqi: | /s/ Liu Zhengqi | |
(Signature) | ||
Signing date: March 7th, 2008 |
Buyers Agent: China National Machinery & Equipment Import & Export Corporation
Address: 12/F 178, Guangan Men Wai Street, Xuan Wu District, Beijing, China
Fx: 0086(0)10-63452264
Ph: 0086(0)10-63452250
Authorized representative: |
| |
(Signature) | ||
Signing date: |
|
Seller: Windtec Systemtechnik Handels GmbH
Address: Schleppeplatz 5,9020 Klagenfurt, Austria
Fx: (0043) 463-444604-44
Ph: (0043) 463-444604-10
Gerald Hehenberger: | /s/ Gerald Hehenberger | |
(Signature) | ||
Signing date: March 7th, 2008 |
7
APPENDIX 1
Single Line Diagram SL3000
8
[Confidential treatment has been requested for the remainder of this exhibit]
9
APPENDIX 2
Main Components in Cabinets for SL3000
cabinet | main components | technical data | ||
+CC3x0 | grid choke | [**] | ||
generator choke | [**] | |||
conntectors | circuit breaker more than [**] | |||
PM3000 | converter | |||
control unit | [**] Components for communication | |||
busbar | [**] per phase lenght [**] meters( not included connections) | |||
high flexible cables | for connections | |||
cabinet | see attached dimensions, protected for vibrations | |||
+PSC100 | Stator Circuit Breaker with min Protection [**] | circuit breaker [**] | ||
Rotor Circiut Breaker with min Protection [**] | circuit breaker [**] | |||
NH-fuse for auxiliary power supply | disconnector functionality | |||
busbar | [**] per phase lenght [**] meters | |||
cabinet | see attached dimensions, protected for vibrations |
10
APPENDIX 3
Dimensions of Cabinets for SL3000
[Confidential treatment has been requested for this exhibit in its entirety.]
11